FORM 201.24-NM2
21
YORK INTERNATIONAL
DELIVERY AND STORAGE
To ensure consistent quality and maximum reliability,
all units are tested and inspected before leaving the fac-
tory. Units are shipped completely assembled and con-
taining refrigerant under pressure. Units are shipped
without export crating unless this has been specified
on the Sales Order.
If the unit is to be put into storage, before installation,
the following precautions should be observed:
Ensure that all openings, such as water connections,
are securely capped.
Do not store where exposed to ambient air tempera-
tures exceeding 42°C.
The unit should be stored in a location where there is
minimal activity to limit the risk of accidental physical
damage.
To prevent inadvertent operation of the pressure relief
devices the unit must not be steam cleaned.
It is recommended that the unit is periodically inspected
during storage.
INSPECTION
Remove any transit packing and inspect the unit to en-
sure that all components have been delivered and that
no damage has occurred during transit. If any damage
is evident, it should be noted on the shipment docu-
mentation and a claim entered according to the instruc-
tions given.
Major damage must be reported immediately to your
local YORK representative.
MOVING THE UNIT
Before moving the unit, ensure that the installation site
is suitable for installing the unit and is capable of sup-
porting the weight of the unit and all associated services.
The units are designed to be lifted using either lifting
chains or a fork lift.
Lifting by Crane / Hoist
A spreader frame should be used to prevent damage to
the unit from the lifting chains.
The unit must only be lifted at the
points provided.
SECTION 3
TRANSPORTATION, HANDLING AND STORAGE
FIG. 4 – LIFTING INFORMATION
3
RIGGING INSTRUCTIONS
AND ESTIMATED SHIPPING
WEIGHT LBS.
LD06926
MODEL
WEIGHT
YCWS0313SC
5568
YCWS0373SC
6244
YCWS0423SC
6578
YCWS0503SC
7649
YCWS0563SC
7784
YCWS0613SC
8619
YCWS0663SC
8736
Summary of Contents for YCWS0313SC
Page 12: ...YORK INTERNATIONAL 12 THIS PAGE INTENTIONALLY LEFT BLANK TO MAINTAIN PAGE FORMAT...
Page 36: ...YORK INTERNATIONAL 36 THIS PAGE INTENTIONALLY LEFT BLANK TO MAINTAIN PAGE FORMAT Commissioning...
Page 86: ...YORK INTERNATIONAL 86 TYPICAL CONTROL PANEL WIRING Maintenance...
Page 87: ...FORM 201 24 NM2 87 YORK INTERNATIONAL TYPICAL CONTROL PANEL WIRING LD06957 8...
Page 103: ...FORM 201 24 NM2 103 YORK INTERNATIONAL NOTES 11...