JOHNSON CONTROLS
91
SECTION 6 – COMMISSIONING
FORM 150.73-NM2
ISSUE DATE: 09/07/2020
6
JOHNSON CONTROLS
1
NEW RELEASE
INSTALLATION AND START-UP CHECKLIST
YLUA
Form 150.73-CL2 (1012)
The following work must be completed in accordance with installation instructions:
CUSTOMER: _________________________________
ADDRESS: __________________________________
PHONE: _____________________________________
JCI TEL NO: ____________________ JCI ORDER NO: ________________ JCI CONTRACT NO: ____________
JOB NAME: _________________________________
LOCATION: _________________________________
CUSTOMER ORDER NO: ______________________
CHILLER MODEL NO
: ____________________________
The work (as checked below) is in process and will be completed by: _____________ / ____________ /
___________
UNIT SERIAL NO
: ___________________________
Month
Day
Year
12. Be certain all water temp sensors are inserted
completely in their respective wells and are
coated with heat conductive compound. ............
13. Assure that evaporator TXV bulbs are strapped
onto the suction lines at 4 or 8 o’clock positions
or suction temp. sensors if EEVs are installed. ....
B. COMPRESSOR HEATERS
(Power On – 24 Hours Prior To Start)
1. Apply 120VAC and verify its value between
terminals 5 and 2 of XTBC2. The voltage should
be /- 10%. ..........................................
2. Power must be applied 24 hours prior to
start-up. ..............................................................
3. Each heater should draw approximately 0.5-1A. ..
C. PANEL CHECKS
(Power On - Both Unit Switch Off)
1. Apply 3-phase power and verify its value.
Voltage imbalance should be no more than 2%
of the average voltage. ......................................
2. Apply 120VAC and verify its value on the
terminal block in the Power Panel. Make the
measurement between terminals 5 and 2 of
XTBC2. The voltage should be /-
10%. ...................................................................
A. UNIT CHECKS
(Checking the system prior to initial start - no
power).
1. Inspect the unit for shipping or installation
damage. .............................................................
2. Assure that all piping has been completed. .......
3. Visually check for refrigerant piping leaks. .........
4. Open suction line ball valve, discharge line ball
valve, and liquid line valve for each system. ......
5. The compressor oil level should be maintained
so that an oil level is visible or splashing in the
sight glass when fully loaded. At shutdown, the
oil level should be between the bottom and
middle of the oil equalizing sight glass. ..............
6. Verify proper CFM of air across evaporator coil.
Verify air flow switch operation. ..........................
7. Check the control panel to ensure it is free of
foreign material (wires, metal chips, etc.). .........
8. Visually inspect wiring (power and control).
Wiring MUST meet N.E.C. and local codes. ......
9. Check tightness of power wiring inside the power
panel on both sides of the motor contactors and
overloads. ..........................................................
10. Check for proper size fuses in main and control
circuits, and verify overload setting corresponds
with RLA and FLA values in electrical tables. ....
11. Assure 120VAC Control Power to TB1 has
15 amp minimum capacity. ................................
Summary of Contents for YLUA0248 Series
Page 4: ...JOHNSON CONTROLS 4 FORM 150 73 NM2 ISSUE DATE 09 07 2020 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 10: ...JOHNSON CONTROLS 10 FORM 150 73 NM2 ISSUE DATE 09 07 2020 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 14: ...JOHNSON CONTROLS 14 FORM 150 73 NM2 ISSUE DATE 09 07 2020 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 30: ...JOHNSON CONTROLS 30 FORM 150 73 NM2 ISSUE DATE 09 07 2020 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 44: ...JOHNSON CONTROLS 44 FORM 150 73 NM2 ISSUE DATE 09 07 2020 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 55: ...JOHNSON CONTROLS 55 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 57: ...JOHNSON CONTROLS 57 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 59: ...JOHNSON CONTROLS 59 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 61: ...JOHNSON CONTROLS 61 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 63: ...JOHNSON CONTROLS 63 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 67: ...JOHNSON CONTROLS 67 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 73: ...JOHNSON CONTROLS 73 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 77: ...JOHNSON CONTROLS 77 SECTION 5 TECHNICAL DATA FORM 150 73 NM2 ISSUE DATE 09 07 2020 5 5 ...
Page 94: ...JOHNSON CONTROLS 94 FORM 150 73 NM2 ISSUE DATE 09 07 2020 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 124: ...JOHNSON CONTROLS 124 FORM 150 73 NM2 ISSUE DATE 09 07 2020 THIS PAGE INTENTIONALLY LEFT BLANK ...