JOHNSON CONTROLS
119
FORM 161.01-OM1
ISSUE DATE: 6/8/2018
5
SECTION 5 - MAINTENANCE
PREVENTATIVE MAINTENANCE
It is the responsibility of the owner to provide the re-
quired daily, monthly and yearly maintenance of the
system.
In any operating system it is most important to provide
planned maintenance and inspection of its functioning
parts to keep it operating at peak efficiency. Therefore,
the following maintenance should be performed when
prescribed.
IMPORTANT – If a unit failure occurs
due to improper maintenance during the
warranty period; Johnson Controls will
not be liable for costs incurred to return
the system to satisfactory operation.
Electrical Isolation
1. Isolate the electrical power supply to the chiller
from the facility
2. Isolate the Power Panel battery from the Uninter-
rupted Power Supply by opening the Power Panel
disconnect switch.
3.
Isolate plant fluid flow to the chiller at appropriate
valves or have refrigerant isolated to prevent free-
wheeling the driveline and generating electrical
energy from the permanent magnet rotor.
TABLE 13 -
MAINTENANCE REQUIREMENTS
Procedure
Daily
Weekly
Monthly
Yearly
Other
Record operating conditions (on applicable Log Form)
X
Check operating parameters for indication of tube fouling or
refrigerant loss
X
Check three-phase voltage and current balance
X
Check programmable operating setpoints and safety cut-outs.
Make sure they are correct for the application
X
Verify condenser and evaporator water flows
X
Leak check and repair leaks as needed
1
X
Check and tighten all electrical connections
X
Clean or backflush VSD heat exchanger
X
Replace VSD starter coolant
X
Measure motor winding and insulation resistance
X
Perform refrigerant analysis
1
X
Review operating data for trends which indicate increasing
vibration or power consumption. The MBC data includes 1 x
rotational speed vibration in displacement.
X
Clean tubes
X
2
Perform Eddy current testing and inspect tubes
2-5 Years
For operating and maintenance requirements listed above, refer to appropriate service literature, or contact your local Johnson Controls
Service Office.
1
This procedure must be performed at the specified time interval by an Industry Certified Technician who has been trained and qualified
to work on this type of YORK equipment. A record of this procedure being successfully carried out must be maintained on file by the
equipment owner should proof of adequate maintenance be required at a later date for warranty validation purposes.
2
More frequent service may be required depending on local operating conditions.
MAINTENANCE REQUIREMENTS FOR YZ CHILLERS
Summary of Contents for YZ MODEL A
Page 10: ...JOHNSON CONTROLS 10 FORM 161 01 OM1 ISSUE DATE 6 8 2018 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 142: ...JOHNSON CONTROLS 142 FORM 161 01 OM1 ISSUE DATE 6 8 2018 Appendix Material Safety Data Sheets...
Page 143: ...JOHNSON CONTROLS 143 Appendix Material Safety Data Sheets FORM 161 01 OM1 ISSUE DATE 6 8 2018...
Page 144: ...JOHNSON CONTROLS 144 FORM 161 01 OM1 ISSUE DATE 6 8 2018 Appendix Material Safety Data Sheets...
Page 145: ...JOHNSON CONTROLS 145 Appendix Material Safety Data Sheets FORM 161 01 OM1 ISSUE DATE 6 8 2018...
Page 146: ...JOHNSON CONTROLS 146 FORM 161 01 OM1 ISSUE DATE 6 8 2018 Appendix Material Safety Data Sheets...
Page 147: ...JOHNSON CONTROLS 147 Appendix Material Safety Data Sheets FORM 161 01 OM1 ISSUE DATE 6 8 2018...
Page 148: ...JOHNSON CONTROLS 148 FORM 161 01 OM1 ISSUE DATE 6 8 2018 Appendix Material Safety Data Sheets...
Page 149: ...JOHNSON CONTROLS 149 Appendix Material Safety Data Sheets FORM 161 01 OM1 ISSUE DATE 6 8 2018...
Page 150: ...JOHNSON CONTROLS 150 FORM 161 01 OM1 ISSUE DATE 6 8 2018 Appendix Material Safety Data Sheets...
Page 151: ...JOHNSON CONTROLS 151 Appendix Material Safety Data Sheets FORM 161 01 OM1 ISSUE DATE 6 8 2018...
Page 152: ...JOHNSON CONTROLS 152 FORM 161 01 OM1 ISSUE DATE 6 8 2018 Appendix Material Safety Data Sheets...
Page 153: ...JOHNSON CONTROLS 153 Appendix Material Safety Data Sheets FORM 161 01 OM1 ISSUE DATE 6 8 2018...
Page 154: ...JOHNSON CONTROLS 154 FORM 161 01 OM1 ISSUE DATE 6 8 2018 Appendix Material Safety Data Sheets...