FINZ Mar 2007

FIG. E: FLUE SYSTEM REQUIREMENTS 

(not to scale)

IMPORTANT INFORMATION

A.  The appliance and flue system shall be installed in compliance with AS/NZS 2918 and the

appropriate requirements of the relevant building code or codes.

B.  Appliances installed in accordance with this standard shall comply with the requirements of

AS/NZS 4013 where required by the regulatory authority i.e. the appliance shall be identifiable

by a compliance plate with the marking “TESTED TO AS/NZS 4013”

C.  Any modification of the appliance that has not been approved in writing by the testing authority

is considered to be in breach of the approval granted for compliance with AS/NZS 4013

D.  Mixing of appliance or flue system components from different sources or modifying the

dimensional specification of components may result in hazardous conditions. Where such

action is considered, the manufacturer should be consulted in the first instance.

E.  Cracked and broken components e.g. glass panels or fire bricks, may render the installation

unsafe.

IF THE A WATERBOOSTER IS FITTED:

Note

: A water booster cannot be fitted in some Clean Air zones (check local council regulations)

A.  Do not connect to an unvented hot water system

B.  Install in accordance with AS 3500.4.1 or NZS 4603 and requirements appropriate to the

relevant building codes.

Seismic Restraint

 

Secure the heater base to the hearth or sub-framing with Dynabolts or similar.

Follow local Council’s Specifications.

More than 3000

3000

or less

60

m

in

.

3000

1000 min. if clear

within 3000 of

flue top

.

3000

Any nearby

structure

.

1000 min. if clear

within 3000 of

flue top

MINIMUM HEIGHT OF FLUE SYSTEM EXIT

NOTE : Dimensions are in millimetres

3000

or less

60

m

in

.

More than 3000

3000

.

Increase from

1000 min. until

clear within

3000 of flue top

Summary of Contents for FINZ

Page 1: ...ue guard fitted 70mm Side Clearance with YUNCA flue guard fitted 160mm Corner Clearance with YUNCA flue guard fitted 60mm G YUNCA Flue Kit 4 2 m x 150 mm stainless steel flue 1 x weather cap cowl 2 4m x 250mm galvanised liner 2 x spider brackets 1 x ceiling tile 1 x secondary shield I Accessory 1200 Flue Guard Kit Additional optional full length guard 1 x 1200 length back guard 1 x 1200 length per...

Page 2: ...case the length of the flue shall not be less than 4 6m from the ash floor protector In some situations the Local Council may vary the above requirements 2 All parts of the chimney exposed to the outside air shall be suitably insulated in accordance with the manufacturers recommendations When loose fill insulation is used in the adjacent ceiling space maintain clearance between the secondary shiel...

Page 3: ...TED Measurements in millimetres A B E F G H 70 160 60 270 500 442 MINIMUM FLOOR PROTECTION MEASUREMENTS WITH YUNCA FLUE MOUNTED SHIELD FITTED Measurements in millimetres C D J K L M N O P 300 100 880 1007 1362 1203 737 680 707 Above Non combustible wall clearances Brick lining from floor to within 25mm of ceiling Leave air vents at the bottom to allow airflow in the cavity If Yunca flue mounted sh...

Page 4: ...ication of components may result in hazardous conditions Where such action is considered the manufacturer should be consulted in the first instance E Cracked and broken components e g glass panels or fire bricks may render the installation unsafe IF THE A WATERBOOSTER IS FITTED Note A water booster cannot be fitted in some Clean Air zones check local council regulations A Do not connect to an unve...