SECTION 2: SYSTEM INSTALLATION
YZ Systems Milton Roy • 201 Ivyland Road • Ivyland, PA • USA • 18974 • P: 281.362.6500 • www.yzsystems.com
NJEX ZEO Version 04/13/2021
Page 19
CAUTION: Excessive tubing lengths should be avoided. Installation of the NJEX ZEO
Odorization system should be as close to the point of injection and Odorant Storage Tank
as possible. Tubing length from the Odorant Storage Tank to the system should not exceed
15 feet (4.5 meters). Discharge tubing length should not exceed 50 feet (15 meters). The
tubing size should be maintained as indicated in this manual. If longer tubing lengths are
required, consult YZ Systems Technical Services at; 800.653.9435 or 1.281.362.6500.
8. Connect the odorant supply source to the odorant inlet bulkhead with the recommended
3/8”
stainless steel tubing (Figure 6 & 8). A tank isolation valve (V15) should be incorporated
between the storage tank and this connection.
9. Connect the process gas source
using ¼” stainless steel tubing regulated to 35-60 psi (2.4-
4.1 Bar) supplied by the NJEX ZEO system owner, with a dielectric union, to the labeled
bulkhead on the back of the system enclosure.
10. Connect the blanket gas line, regulated to 10-25 psi (0.7-1.7 Bar)
using ¼” stainless steel
tubing with a dielectric union at the fitting located at the odorant supply tank that leads to the
labeled bulkhead on the back of the system enclosure.
11. Connect the discharge tubing bulkh
ead using ¼” stainless steel tubing to the pipeline
connection using a dielectric union and check valve.
Figure 5 Redundancy Wiring Diagram