Pipe diameter,
mm
Melting depth,
mm
Heatingtime, s Melting time, s Cooling time, s
20
14
5
4
3
25
16
7
4
3
32
20
8
4
4
40
21
12
6
4
50
22,5
18
6
5
63
24
24
6
6
1.prior to operation
1.1. Power source.
Ensure that the power source to be utilized
conforms to the power requirements spec-
ified on the product nameplate.
1.2. «On\Off» switch.
Ensure that the power switch is in the OFF
position. If
the plug is connected to a receptacle while
the power switch is in the ON position, the
power tool will start operating immediate-
ly, inviting serious accident.
1.3. Extension cord.
When the work area is removed from the
power source use an extension cord of suf-
ficient thickness and rated capacity. The
extension cord should be kept as short as
practicable.
2. how to use\
2.1.
Connecting to mains
Pipe welding machine must be connected
to the earthed receptacle with a protective
conductor.
2.2.
Choice of heating sockets
The choice of heating sockets for heating
element is made based on size of pipes to
be welded.
They are installed on heating element by
allen wrench from standard set.
Depending on requirements and machine
model several heating sockets can be in-
stalled on heating element.
2.3.
Operating temperature control
To provide operating temperature stabil-
ity, heating element of the machine is
equipped with stepped temperature con-
trol. Operating temperature is fixed to 260
± 10°C.
Follow pipes, fittings manufactures’ in-
structions!
Before operation check temperature on
working surfaces of heating sockets in-
stalled on the heating element.
2.4.
Warm-up
Manufacturer sets operating temperature
of pipe welding machines to 260°С. De-
pending on pipe material, necessity to
change this value may occur. Before op-
eration familiarize yourself with informa-
tion from pipes and formed parts manu-
facturer!
It is recommended to control temperature
of heating sockets of the heating element
(heating fittings), for example with the
help of surface thermometer. If necessary,
temperature can be adjusted by turning the
temperature control. When adjusting tem-
perature remember that heating element is
ready for operation only after 10 minutes
after reaching the set temperature.