Installation & Operation • 19
INSTALLATION & OpERATION
Kickplates
Each case is shipped with a front kickplate. Cases with end panels are
shipped with 1 side kickplate per end panel. Cases that join together are
shipped with a kickplate splice.
Front and side kickplates are attached to the case bases using Tinnerman
clips. Position the front kickplate so the flange is on top and facing outward.
The screw (supplied) goes through the kickplate and into the Tinnerman clip
(
There is a natural gap between the top of the kickplate and the underside
of the Crystal Merchandiser
®
that allows airflow of 50 CFM per door. If more
airflow is required, contact the factory to order optional louvered kickplates
(provides 150 CFM per door).
Bumper
Cases are supplied with a 3" protective bumper shipped loose on top of
each case. Each case has its own bumper assembly, including end caps.
The steel bumper support and snap track are factory-installed on the front of
the case. The bumper may need trimming before snapping it onto the snap
track.
Door leveling must be completed before attaching the bumper (
Leveling (Door Sag/Sawtooth)" on page 17
Top Trim
Top trim is factory-installed, and it hides the door hardware located on the
top exterior of the case. Joint splices are shipped loose and must be field-
installed at the upper case joints.
CoolView
®
Doors
Door leveling must be completed before attaching the bumper and kickplate
(
See "Door Leveling (Door Sag/Sawtooth)" on page 17
).
COOLARC
™
DOOR HANDLES
CoolView
®
ultra
™
doors use the CoolArc
™
door handle. The CoolArc
™
door
handle is attached to the glass surface of the door by an industrial-grade
adhesive.
HOLD-OPEN BRACKET
CoolView
®
doors are self-closing, and closing tension increases as the door
opens wider. The hold-open bracket keeps the door open when engaged,
which is useful for stocking shelves or case maintenance. To engage the hold-
open bracket, open the door to at least 90° until it clicks. Closing the door to
about 80° will release tension on the door, and it will self close again.
FIGURE 24: Kickplate Installation
1. Install Tinnerman clip at each base.
2. Position side kickplate.
3.
Position front kickplate with top flange facing outward.
4. Insert fasteners to secure the front and side kickplates
to the Tinnerman clips.
Front Kickplate
Side Kickplate
Tinnerman Clip
Base
FIGURE 25: Hold-Open Bracket