16  •  Refrigeration

REfRIgERATION

Off-Cycle Defrost

Periodic defrosting is necessary to keep the evaporator coil free of frost. 

See Figure 23 

for defrost settings.

During off-cycle defrost, refrigerant is stopped either by stopping the compressor or by closing the liquid line solenoid valve and allowing the 

compressor to pump down. The fans and lights remain on during off-cycle defrost.

If temperature termination is selected, set the termination temperature for 45°F for discharge air and coil temperature. 

Note: Opening the 

doors, stocking product, or shopping during off-cycle defrost may cause premature defrost termination.

Case Thermometer

An NSF thermometer is shipped loose and should be installed in the warmest product location as required by NSF. Specific field installation 

instructions are packaged with the NSF thermometer.

SETTING

ORMC83D

ORMC88D

Evap Temp

28°F

28°F

Condensing Unit Cut-In

74 psig

74 psig

Condensing Unit Cut-Out

62 psig

62 psig

Return Air Temperature Cut-In

37°F

37°F

Return Air Temperature Cut-Out

33°F

33°F

Discharge Air Temperature Cut-In

34°F

34°F

Discharge Air Temperature Cut-Out

30°F

30°F

Superheat Setting *

8°F

8°F

Note: For high-glide refrigerants, use dew point for unit sizing. Adjust evaporator 

pressure as needed to maintain discharge air temperatures. To receive the full 

benefit of high-glide refrigerant properties, the superheat may need to be lowered 

to 4-6°F. Contact Zero Zone with questions.

 FIGURE 22: Case Temperature Internal Control Options (R-404A)

SETTING

ORMC83D

ORMC88D

Defrost Type

Off-Cycle

Off-Cycle

Frequency

2 Per Day

2 Per Day

Duration

30 Minutes

30 Minutes

 FIGURE 23: Defrost Settings

Summary of Contents for Reveal Merchandiser ORMC83D

Page 1: ...ZERO ZONE REVEAL MERCHANDISER MULTI DECKS WITH DOORS With CoolView Ultra Doors ChillBrite LED Lighting INSTALLATION OPERATION MANUAL COMPLIANT 66 0109 REV C May 2021...

Page 2: ...op Mounting Plate 10 Drain 10 Kickplates 11 Bumper 11 Top Trim Splice 11 CoolView Doors 11 CoolArc Door Handles 11 Door Closer Adjusting Door Tension 11 Hold Open Bracket 12 Door Gasket 12 Removing a...

Page 3: ...rther consideration the Seller will extend to the original purchaser prior to shipment a limited extended warranty on the compressor only following expiration of the standard warranty The Seller agree...

Page 4: ...frigeration technicians If any questions or problems arise call Zero Zone at 800 247 4496 Any change to a Zero Zone product made during the installation start up or at any other time must be submitted...

Page 5: ...d Freezers ANSI Approved equipment certified by ETL ASHRAE Standard 72 Method of Testing Commercial Refrigerators and Freezers ANSI Approved AHRI 1200 Performance Rating of Commercial Refrigerated Dis...

Page 6: ...Every case in a lineup has a packet attached to the shelving that contains important information about the case and or lineup and if applicable special instructions for installing ordered options Bump...

Page 7: ...anels Do not place them under the bumper support or drain pipe as that will crush the components Cases have steel protective support plates under the end panels not under insulated dividers to protect...

Page 8: ...ch base to equal the highest point Shims should not extend beyond the front case bases or they will interfere with installing trim The shims should be oriented to sit under the front and rear bends of...

Page 9: ...peration 7 Installation Operation Figure 6 Reveal Merchandiser Base Locations 4ORMC 6ORMC 8ORMC 12ORMC Drawings are top views with bases shown under the case Case length does not include end panels 1...

Page 10: ...with Butyl caulk before setting the next case in the lineup Case caulking instructions and caulk are shipped with every case See Figure 8 on page 9 Move the next case into position and bolt it to the...

Page 11: ...e to ensure a tight seal 3 Repeat this process between each case in the lineup SURFACES TO BE CAULKED MUST BE CLEAN DRY AND FREE OF FROST ABOVE 40 F Note NSF sealant must be applied with no gaps to se...

Page 12: ...ccess the top mounting plate remove the top trim piece This will require a Phillips bit and a 1 4 hex screw bit 2 Loosen all 3 screws that secure the slotted plate by 2 turns See Figure 12 Do not remo...

Page 13: ...he spring tension to the door This means that the square pin must be aligned with the square opening when installing a door An adjustment screw on the front can be used to increase or decrease tension...

Page 14: ...oes not close on its own This removes tension between the door and torque adjuster 3 Remove shoulder bolt and bushing on the top of the hinge side of the door See Figure 17 Only remove the bolt holdin...

Page 15: ...Duty 22 2 Position 0 10 250 150 4 Position 0 5 10 15 250 250 150 100 24 2 Position 0 10 250 150 4 Position 0 5 10 15 250 250 150 100 Solid Shelf Heavy Duty 22 2 Position 0 10 350 275 4 Position 0 5 1...

Page 16: ...ided inside the case on the right hand side of the coil for venting and draining the system Refrigerant Piping Correct refrigeration line sizing and industry standard installation practices are essent...

Page 17: ...Refrigeration 15 Refrigeration Figure 21 R 404A Line Sizing Tables for Zero Zone Cooler 28 F Evaporator Temperature...

Page 18: ...uct location as required by NSF Specific field installation instructions are packaged with the NSF thermometer SETTING ORMC83D ORMC88D Evap Temp 28 F 28 F Condensing Unit Cut In 74 psig 74 psig Conden...

Page 19: ...diagram with off cycle defrost Note Always refer to the wiring diagram shipped with the case Optional top electrical will be located in a junction box on top of the case External wiring should be size...

Page 20: ...nd warm water or a mild sanitizer 6 If the case is equipped with a condensate pan and pump the drain should be blocked before washing coils Water can be removed with a shop vacuum 7 Coils may be clean...

Page 21: ...2021 Zero Zone Inc All Rights Reserved May 2021 For other technical support please refer to the Technical Resources page at WWW ZERO ZONE COM or contact the Zero Zone Service Department at 800 247 44...

Reviews: