03 • Remove caps and pins from motor
• Before installing motor, remove caps and
pins from motor.
• At the end of the installation, put back
plastic covers for a better visual finish of
the operator.
04 • Install operator on the supports
• The operator must be placed on both
supports the same time to avoid
leaving the operator suspended by only
one of the supports.
To make the task easier, you should unlock
the operator in order to be able to stretch
/ retract arm easily,to get the correct posi
-
tion for supports.
05 • Test movement
• Install the pins removed earlier on each
place with a small amount of lubricant for
less friction.
•Move the door manually to see if the
door opens and closes uniformly and cor-
rectly, without any irregular friction during
its entire travel;
This will ensure that operator is not
subjected to problems during operation.
06 • Connecting operator to control board
and configuring control devices.
•With the operator installed, connect it to
control board for system configuration (see
control board user manual).
Must also configure the desired control
devices (transmitters, wall switch, etc.) and
other additional components such as an
-
tenna, warning light, key selector, among
others.
It is important to respect this installation order!
Otherwise, it is not possible to ensure correct installation and operators may not