PREMIER AD INSTALLATION MANUAL.
Software Version :PANEL-R1578 & LOOP-R1062
Approved Document No: GLT.MAN-105A
PAGE 2
Issue : 2.02 Authorised: GH Date: 16/07/2007
1.INTRODUCTION
THIS FIRE ALARM CONTROL PANEL IS CLASS 1 EQUIPMENT AND MUST BE
EARTHED
This equipment must be installed and maintained by a qualified and technically experienced person.
1.1 HANDLING THE PCBS
If the PCBs are to be removed to ease fitting the enclosure and cables, care must be taken to
avoid damage by static.
The best method is to wear an earth strap, but touching any earth point (eg building plumbing) will help to
discharge any static. Hold PCBs by their sides, avoiding contact with any components.
Always handle PCBs by their sides and avoid touching the legs of any components. Keep the PCBs away from
damp dirty areas, e.g. in a small cardboard box.
1.2 USING THIS MANUAL
This manual explains, in a step-by-step manner, the procedure for the installation of the
Premier AD
Range of
Fire Alarm Control Panels. For full operational and maintenance information, please refer to document
GLT.MAN-106 (USER MANUAL, MAINTENANCE GUIDE & LOG BOOK). It also contains a System set-up
table, and Installation Certificate, that must be completed by the Commissioning Engineer prior to system
handover.
Unlike the User Manual, this Installation Manual must not be left accessible to the User.
1.3 ABOUT THE PREMIER AD FIRE ALARM PANEL & INTEGRAL PSE
1.4 DESIGNING THE SYSTEM
This manual is not designed to teach Fire Alarm System design. It is assumed that the System has
been designed by a competent person, and that the installer has an understanding of Fire Alarm
System components and their use.
We strongly recommend consultation with a suitably qualified, competent person regarding the
design of the Fire Alarm System. The System must be commissioned and serviced in accordance
with our instructions and the relevant National Standards. Contact the Fire Officer concerned with
the property at an early stage in case he has any special requirements.
If in doubt, read BS 5839: Pt 1: 2002 “Fire Detection and Alarm Systems for buildings (Code of
Practice for System Design, Installation, commissioning and maintenance)” available from the BSI, or
at your local reference library.
1.5 EQUIPMENT GUARANTEE
If this equipment is not fitted and commissioned according to our guidelines, and the relevant
National Standards, by an approved and competent person or organisation, the warrantee may
become void.
•
The PREMIER AD Fire alarm control panel is a
two loop analogue addressable Fire Alarm
Control Panel, with the loops split into 16 Zones.
•
It has 4 sounder output circuits each capable of
supplying 250mA.
•
It has a set of fire relay contacts (voltage free) rated
at 1A SELV.
•
It has a set of fault relay contacts (voltage free)
rated at 1A SELV. This relay is normally
powered to allow a fault output in the case of
total power failure.
•
It has a class change connection to allow remote
activation of the sounders. (not required by
EN54-2)
•
It has an RS485 repeater connection.
•
It has the ability to disable any address, any zone
or any of the sounder circuits.
•
It has a one man test mode, which resets the zone
in test after 8 seconds.(EN54 option with
requirements).
•
It has a maximum battery capacity of 7 Ah.
•
It will operate in ambient temperatures of –5 to
40
o
C
•
It will operate in a relative humidity of up to 93%
(non condensing)
•
It will withstand vibrations between 5 & 150 Hz
•
It has a maximum capacity of 32 devices per zone
•
The PSE is linear, with a 1.5A output at system
voltage (18-32V)
•
The mains supply is filtered before entering the
transformer.
•
The charger & battery are both fused at 2.5A (time
delay)
•
The PSE will draw a maximum of 25uA from the
battery in the event of mains failure. (the FACP
will continue to take around 60mA)
•
The FACP & PSE should be maintained as
described in section 3 of the User Manual,
Maintenance Guide & Log Book.
Summary of Contents for NPAD 2
Page 1: ...INSTALLATION MANUAL...