41 Installation and Operating Instructions V04
7 Commissioning
7.1 Electrical checks
Carry out the main electrical checks as follows:
①
Check the PE connection with a multimeter: check that the inverter’s exposed metal
surface has a ground connection.
②
Check the DC voltage values: check that the open-circuit voltage of the PV array
on the coldest day based on statistical records does not exceed 600V.
③
Check the polarity of the DC voltage: make sure the DC connectors have the
correct polarity.
④
Check the PV array’s insulation to ground with a multimeter: make sure that the
insulation resistance to ground is greater than 1 Mohm.
⑤
Check and make sure that the AC circuit breaker must be correctly rated and
mounted.
Risk of injury due to incorrect installation
We strongly recommend carrying out preliminary checks before commissioning to
avoid possible damage to the device caused by incorrect installation.
Danger to life due to the presence of DC voltage
• Only touch the insulation of the PV array cables.
• Do not touch parts of the sub-structure and frame of PV array which are not
grouned.
• Wear personal protective equipment such as insulating gloves.