Page D-2
The actual procedures for using the Break-out Box
are the same for CruiseCommand and
ClearCommand Processors. However, the
adjustment within the Processor to obtain the correct
output may differ. The appropriate Installation
Manual must be referred to when making the
adjustments.
Procedure: Throttle Signal
Testing
Depending on which Processor is being tested, it may
have the capability of sourcing one or all of the
following: DC Voltage, Current, PWM (Pulse Width
Modulation) or Frequency.
DC Voltage
A) Ensure that power is removed from the Engine
Electronics and the Processor.
B) Disconnect the Throttle Harness from the number
1 Processor connector/pigtail.
C) Insert the Break-out Box between the number 1
Processor connector/pigtail and the Throttle
Harness as shown in Figure D-4.
FIGURE D-4: THROTTLE CONNECTION (DC VOLTAGE)
D) Set up the Multimeter to measure DC Volts and
plug the black lead into the Break-out Box black
socket labeled “-” and the red lead into the socket
labeled “VDC”.
E) Turn power ‘On’ to the Processor and take
command at any Remote Station.
F) The appropriate Idle Voltage for the application
should be measured at this time.
G) Move the Control Head lever to the Full Throttle
position while depressing the Transfer Button
(Throttle Only Mode).
H) The appropriate Full Throttle Voltage for the
application should be measured at this time.
Current (mA)
A) Ensure power is removed from both the Engine
Electronics and the Processor.
B) Disconnect the Throttle Harness from the number
1 Processor connector/pigtail.
C) Insert the Break-out Box between the number 1
Processor connector/pigtail and the Throttle
Harness as shown in Figure D-5.
D) Set up the Multimeter to measure current (mA.)
and plug the black lead into the Break-out Box
black socket labeled “-” and the red lead into the
socket labeled “mA”.
E) Turn power ‘On’ to the Processor and take
command at any Remote Station.
F) Depress and hold the Push-button Switch labeled
“mA.” The appropriate Current (mA.) for the
application should be measured.
G) Move the Control Head lever to the Full Throttle
position while depressing the Transfer Button
(Throttle Only Mode).
3
Gray 12
Pin
Clutch
Connector/
Pigtail
The external
connections for
Clutch Power,
Ahead, Astern,
and Neutral
Solenoids, Troll
On/ Off, and
Proportional
Solenoids are
made at this
connector/
pigtail.
4
Gray 8
Pin
Control Head
Connector
All the required
connections for
the Remote
Control Stations
are made at
these
connectors.
5
Gray 6
Pin
Serial
Communication
Connector/
Pigtail
The Serial
Communication
connections
between
multiple
Processors in
applications
with more than
one Processor
at this
connector/
pigtail.
6
Gray 4
Pin
Tachometer
Sensor
Connector/
Pigtail
The input signal
from a
Tachometer or
Shaft Speed
Sensor
connects to this
connector/
pigtail.
NOTE:
The following procedures and drawings
pertain to both the CruiseCommand and
ClearCommand Processors.
Designation
#
Description
Harness Type
Harness Use
Summary of Contents for ClearCommand 9000 Series
Page 132: ......
Page 133: ...APPENDIX A...
Page 134: ......
Page 139: ......
Page 140: ...Page A 4...
Page 143: ......
Page 144: ...10...
Page 148: ...Page A 18...
Page 149: ...Page A 19 TEMPLATE...
Page 150: ...Page A 20...
Page 152: ...Page A 22...
Page 154: ...Page A 24...
Page 156: ...Page A 26...
Page 157: ...Page A 27 Drawing 11488D 1 Twin Screw Single APS Connection Alternate Remote Switch...
Page 158: ...Page A 28...
Page 159: ...Page A 29 Drawing 11488D 2 Twin Screw Dual APS Connections...
Page 160: ...Page A 30...
Page 161: ...Page A 31 Drawing 11488D 3 APS Notes Page...
Page 162: ...Page A 32...
Page 164: ...Page A 34...
Page 166: ...Page A 36...
Page 170: ...Page A 40...
Page 172: ...Page A 42...
Page 176: ...Page A 46...
Page 178: ...Page C 48 ZF Mathers LLC 12125 Harbour Reach Drive Suite B Mukilteo WA 98275...
Page 179: ...APPENDIX B...
Page 180: ......
Page 234: ...Appendix B 6...
Page 238: ...Appendix B 10...
Page 242: ...Appendix B 14...
Page 247: ...Service Field Test Unit Reference Manual MM13927 Rev E 4 07...
Page 248: ......
Page 250: ...Page ii Table of Contents...
Page 264: ...SERVICE FIELD TEST UNIT MM13927 RvD 10 03 Page 3 2...
Page 265: ...APPENDIX C...
Page 266: ......
Page 267: ...Appendix C 1 Drawing 12284A 1 ClearCommand Diagram all options...
Page 268: ...Appendix C 2...
Page 269: ...Appendix C 3 Drawing 12284A 2 ClearCommand Circuit Board Connections...
Page 270: ...Appendix C 4...
Page 271: ...Appendix C 5 Drawing 12284A 3 ClearCommand Drawing Notes Page...
Page 272: ...Appendix C 6...