Start - up
1. Ambient temperature:
Design
max.
min.
4. Electrical connection
400V - 3 - 50 Hz
Standard version.
20 °C
42 °C
+ 5 °C
Or according to order, type plate, wiring -
Tropical version:
35 °C
45 °C
+ 5 °C
diagram
Water temperature
Check voltage:
Standard version.
15 °C
> 5 °C
Max. deviation is +5% / -10%
Tropical version:
25 °C
> 5 °C
Check phase sequence:
When the phases are not in the correct order,
2. Installation place:
the direction of the auger is reversed.
The distance between condenser (air outlet) and wall
The ice then is pressed down onto the bearing
or ceiling respectively shall at least be 75 cm,
instead upwards, damaging the seal.
see data sheet.
(Phase sequence relay: see page 3, point 10)
Provide sufficient room ventilation.
Observe the arrow indicating the
direction of rotation
Prevent any heat build-up.
Especially the air outlet of the condenser must be free
Provide at site:
and at least 1,5 to 2,5 times larger in diameter than the
Provide main switch and fuses according to
condenser itself.
wiring diagram. Make firm installation to mains
power supply, do not use a plug-and-socket
connection in order to avoid later erroneous
At higher air temperatures (above 20°C resp. 35°C),
interchange of phases.
or insufficient ventilation of the machine,
Tighten all electrical connections in the control
and at water temperatures above 15°C resp. 25°C
panel, as they may have loosened during.
the production capacity may decrease.
transport
Crankcase heater:
3. Water connection
After connecting the machine to electricity
the start-up is possible only after abt. 1 hr.
The machine works with normal potable water.
(Preheating - see page 3 point 9)
With harder water above 20° d.H. install a water-
softener.
5. Cut-Out of machine when storage bin
If the water is slightly saline, or comes from a well
or ice car is full:
or is outside 6,5 - 9,5 pH consult ZIEGRA
See page 3 point 2 .
for accordingly advice.
and contact our service department
Provide at site:
Rigid piping or high-pressure hose.
6. Start:
If long supply lines necessary,
Ice production starts after approx. 2 min.
insulate, if possible.
Water pressure 2 - 4 bar
7. V-Belt:
Provide water overflow hose
Check after 2-8 days and tighten, if necessary.
8 Ice discharge
Fasten tube to the ice discharge slightly with the clamp. Put on the insulation.
The ice must leave the outlet freely and without clogging.
Otherwise the freezing unit and gearbox will be overloaded.
Extension of ice discharge tube.
Enlargen diameter, no sharp curbs. Only use tubes
with smooth inner surface, without edges or ridges.
Ice must slide downwards only,
not horizontically or upwards.
Further advice in the extra folder "Installation Ice discharge"
2