Portable Drying Unit (PDU)

Quick Start Guide

WARMING PDU

1.  Ensure that the Portable Drying Unit (PDU) batteries are fully charged (see “Charging the Battery” 

section below for details on charging the batteries).

2.  Connect the battery to the PDU by opening the compartment on the front right hand side of the 

PDU and connecting the male and female white clips. Place the connected battery into the battery 

storage compartment.

3.  Push the ‘Power’ switch on the front interface to the ‘Hot’ position. This will turn on the red LED 

light adjacent to the ‘Hot’ label. The PDU is now heating up and will require approximately 30 

minutes to reach its set temperature. The current internal temperature is shown on the thermostat 

on the front interface. Ensure that the lid is closed to minimise the time required to reach the set 

temperature. (Note: The PDU will heat to a temperature that is pre-set by Ziltek. If this temperature 

requires changing, consult the ‘Portable Drying Unit Operating Instructions’ in the RemScan Oper-

ational Manual for detailted instructions on changing the set temperature).

4.  Once the PDU has reached its set temperature, sample drying may be commenced.

SAMPLE PREPARATION

1.  Label each sample slide with a marker pen for easy identification of individual samples.

2.  Place wet soil samples onto sample slides, preferably designating one sample per slide. 

i. 

For sandy and loamy soil types, spread the sample evenly into the five slide wells and flatten 

the surfaces with a spatula to remove excess soil present until the soil level sits slightly 

above the well level. 

ii.  For clay soil types, samples can be spread on the back of the sample slides using a spatula 

until all of the knurling is covered to increase the surface area and increase drying efficiency. 

SAMPLE DRYING

1.  Place the loaded sample slides onto the provided drying rack and place the rack into the PDU.

2.  Close the lid and allow the samples to dry.

3.  Avoid opening the PDU during the drying process to prevent heat loss and therefore minimise 

drying time.

4.  After 30-60 minutes (depending on sample wetness), the drying rack containing the dried samples 

can be removed from the PDU.

SCANNING SAMPLES

1.  For sample slides containing five filled wells, tamp the surfaces of each well flat using the tamper 

provided in the RemScan kit.

2.  Scan each well with RemScan using the instructions in the ‘RemScan Quick Start Guide’. Each 

well can be used as a sub-sample for a total of five per unique sample.

3.  For clay samples loaded onto the back of the sample slides, simply tamp the soil surface and scan 

five times at different locations on the slide with RemScan.

Z051-03  01/20

P +61 (0)8 8152 9390 

E info@ziltek.com 

W ziltek.com