Chapter 3: Configuration and commissioning
ZP2 Series Installation Manual
107
Commissioning
After the control panel and corresponding devices are installed and configured,
the system must be commissioned.
Check the following:
•
That the fire system is designed in accordance with all required regulations
and standards
•
That the maximum alarm current in your installation does not exceed the
maximum current specifications of the power supply
•
That all equipment is correctly installed and tested and that all cabling
complies with the recommendations outlined in “Recommended cables” on
page 24
•
That all software functions are correctly programmed
•
That all installed detectors are appropriate for installation environment and
operate correctly
•
That all inputs and outputs operate correctly
•
That any input/output logic (rules and actions) configuration is correct
•
That the fire system is functioning correctly in standby and is not reporting
any alarms or faults
•
That under the alarm conditions (with all applicable devices activated), the
current consumption does not exceed the power supply specifications (if the
batteries are not activated the current consumption is within the
specifications)
Summary of Contents for ZP2 Series
Page 1: ...ZP2 Series Installation Manual P N 00 3251 501 0003 04 ISS 04MAY15...
Page 6: ...iv ZP2 Series Installation Manual...
Page 20: ...Chapter 1 Introduction 14 ZP2 Series Installation Manual...
Page 114: ...Chapter 3 Configuration and commissioning 108 ZP2 Series Installation Manual...
Page 128: ...Chapter 5 Technical specifications 122 ZP2 Series Installation Manual...
Page 142: ...Appendix C Menu maps 136 ZP2 Series Installation Manual...
Page 148: ......