FBL200/300 Flap Barrier
User Manual
P a g e
| 8
4
Equipment Installation and Commissioning
Device Installation
4.1
Prepare the tools for installing the equipment, and check the accessories according to the packing
list.
After clarifying the system composition and working methods, carry out overall planning and
prepare to start installation.
After finishing the foundation surface for installing the equipment, arrange the equipment.
After locating the holes, drill the holes and embed M12 anchor bolts or expansion bolts.
Thread the high-current cable and the weak-current cable with 3/4" PVC pipes and bury them in
the corresponding positions with cement.
Move each chassis to the corresponding installation position first align the anchor bolt positions
one by one.
Check whether the system composition and working method are correct, and then proceed to the
next step after the check is correct.
Open the cabinet door, choose one of the devices as the reference datum (preferably choose the
middle one as the reference datum), align the bolt holes of the machine base with the
corresponding anchor bolts, and pre-tighten the nuts.
Open the door of an adjacent chassis, align the bolt holes of the machine base with the anchor
bolts and align the set reference equipment, pre-tighten the nuts; if there is more than one need to
install and so on.
Refer to the wiring diagram, connect the power line and control line, and connect the system
protection ground line.
Tighten the anchor nut after the state inspection and function debugging are qualified.