2
2. Rotating the arms to the connection points until it was
fastening, and use the Hex key to fasten the one screw
on each arm, as shown in Figure 2-2.
Figure 2-2
2.2 Power-on test before the installation of device
1. Please make sure that the power requirements are strictly met to avoid permanent damage to the unit. Input voltage: AC
100~120V /200~240V.
Note:
The tripod turnstile must be connected to the ground (earth).
2. Power on and wait 30s for the tripod turnstile to finish the self-check program.
3. Lift the arms manually, as shown in Figure 2-4.
4. Check whether the tripod turnstile and the LED indicators work properly.
If there is any problem, please contact the supplier.
Figure 2-3
Figure 2-4
3. Equipment Installation
3.1 Installation conditions
The equipment must be installed on concrete ground, ensuring that expansion bolts can be secured firmly.
You are suggested to install an assistant framework or fence to form a passageway, as shown in Figure 3-1.
Lift upwards
Tighten the one screw on each
arm in clockwise direction.
Earth wiring terminal
There is a power switch in the side
direction of this power supply.