Pelletherm V.2 M01 29
6. COMMISSIONING OF THE EQUIPMENT.
6.1. MAIN REQUIREMENTS FOR THE FUEL USED.
Upon commissioning of hot-water boiler "Pelletherm V.2 M01" there must be met the
following requirements for the fuel:
In order to achieve complete combustion it is necessary to be used only dry fuel
meeting the requirements of standard EN ISO 17225-2:2014, class A1, A2 and B and
developed by the manufacturer methodology for categorization of pellets;
It is forbidden to store the fuel in close proximity to the boiler or at a distance less
than 400 mm from it;
The optimal distance which the manufacturer recommends between the boiler and
the fuel is at least 1000 mm. It is advisable the fuel to be stored in an adjacent
premise;
Fire safety regulations must be complied with when installing hot-water pellet boiler
series "Pelletherm V.2 M01" and storage of the fuel. It is recommended that at a
convenient and safe place to be mounted a fire extinguisher.
Hot-water pellet boiler "Pelletherm V.2 M01" is commissioning only by
specialized company authorized to this activity.
6.2. COMMISSIONING OF BOILER "PELLETHERM V.2 M01".
Upon commissioning of hot-water boiler "Pelletherm V.2 M01" there must be met the
following basic requirements:
Servicing of the hot-water pellet boiler must be carried out in accordance with the
instructions for maintenance and operation;
Any interference in the work of the system, which could lead to a potential health
hazard to staff or indirectly related parties is inadmissible;
During operation of the system, it should be periodically be checked by the servicing
staff/client;
The user should not perform any repairs on the boiler modules. When a problem
occurs during operation, it should be sought professional help from the company
servicing it;
The ash from the combustion process is collected in fireproof containers with covers
and after is being cooled down to ambient temperature is disposed in the appropriate
places.
It is prohibited increasing the thermal power of the burner and respectively the
boiler above the maximum.
When installing pellet boiler "Pelletherm V.2 M01" and tank for feed the
bunker with pellets boiler local fire requirements must be respected..
6.2.1. INTERFACE CONTROL BOARD OF BOILER "PELLETHERM V.2 M01".
Figure 6.1 presents a view of the interface panel with display and keyboard to control hot-
water boiler "Pelletherm V.2 M01".