The modules in a PV array should be regularly checked for damage. Factors such as glass breakage,

cable breakage, and junction box damage may lead to function and safety problems. In the case of a
damaged module, replace it with the same type of module. Refer to the Product Installation Manual for
installation and disassembly of module.

Check that mounting hardware is properly tightened.

Check that all string fuses in each non/earthed pole are operating.

Replacement modules must be of same type. Do NOT touch live parts of cables and connectors. Use
appropriate safety equipment (insulated tools, insulating gloves, etc.) when handling modules.

Cover the front surface of modules by an opaque material when repairing. Modules when exposed
to sunlight generate high voltage and are dangerous.

PV modules are equipped with bypass diodes in the junction box. This minimizes module heating
and current losses. Do NOT open the junction box to change the diodes even if they malfunction.

In the event that a module is damaged (broken glass or a scratch on back sheet) and needs to be
replaced.

10.2 CONNECTOR AND CABLE INSPECTION

Inspect all cables to verify that connections are tight; the cables are protected from direct sunlight

and sited away from areas of water collection.

It is recommended to check the torque of terminal bolts and the general condition of wiring at least

once a year. Also, check that mounting hardware is properly torqued. Loose connections will result in
damage to the array.
10.3 CLEANNING

The amount of electricity generated by a solar module is proportional to the amount of light falling

on it. A module with shaded cells will produce less energy and therefore it is important to keep modules
clean.

Clean PV modules when the irradiance is below 200W/m2; liquid with a large temperature
difference from the modules shall not be used for cleaning the modules;

It is forbidden to clean PV modules under the weather conditions of wind more than 4 grades, heavy
rain or heavy snow;

When cleaning with pressurized water, the water pressure on the glass surface of the module shall
not exceed 700 KPa (14619.80psf); the module is prohibited to bear the extra force;

When cleaning PV modules, do NOT step on the modules; do NOT spay water on the backside of
the module or the cables; do NOT clean the backside of the modules; keep the connectors clean and
dry; prevent fire and electrical shock from occurring; do NOT use as steam cleaner;

Summary of Contents for ZXM6- TD72- 370/M

Page 1: ...Installation Manual for Double Glass June 27 2018...

Page 2: ...Clamped installation 3 6 1 Module overview 3 6 2 Material list 4 6 3Installation method 5 6 4 Compatibility of ZNSHINE SOLAR AUSTRALIA PTY LTD clamp clamped with each frame system 6 6 6 Selection sche...

Page 3: ...ng shall be firstly fused and then connected to other modules strings For the maximum fuse rating please refer to the detailed specifications in the last page 2 3 Photovoltaic PV modules will generate...

Page 4: ...required a dry and ventilated room shall be used 3 3 When unpacking the modules shall be handled by both hands Don t place the modules in an overlapping mode 3 4 The double glass modules should be car...

Page 5: ...beaches or land fill areas that are prone to suffer from pluvial erosion 5 2 4 Please don t install the PV modules in areas where they may be immersed in water or continuously exposed to a sprinkler o...

Page 6: ...pressing block type installation system Item Name Picture Dimension mm Material 1 Clamp Length and width 150 50 Aluminumalloy6063 2 Clamp splice Length and width 150 60 Aluminumalloy6063 3 EPDM Lengt...

Page 7: ...ter and firstly get familiar with the whole process and then start the installation In addition please complete all the site preparations before installation Installation suitable for double glass pre...

Page 8: ...tighten the nuts M6SS304 6N m 8N m Place the clamp inside the track on the frame M8SS304 Insert the module into the pressing block and install the pressing block and finally tighten the nuts M8ss304...

Page 9: ...r not Please find the following dimensions before evaluating the frame system If it is required to change the screw size please contact ZNSHINE SOLAR AUSTRALIA PTY LTD please note that the unit used i...

Page 10: ...to use the T type cap Example B C type steel frame installation ZNSHINE SOLAR AUSTRALIA PTY LTD recommends using M8 bolt fixing clamp The tightening torque of M8screw is 16 20N M In the selection of c...

Page 11: ...load pressure Clamp length Mounting direction 60pcs Double Glass 2400 1 5 Pa 1600 1 5Pa 150mm The above distance refers to that from edge of module to center of clamp 72pcs Double Glass 1600 1 5Pa 16...

Page 12: ...10...

Page 13: ...e ZNSHINE SOLAR AUSTRALIA PTY LTD PV modules connected in serial should be installed in accordance with the same orientation and angle Any different orientations or angles may result in the different...

Page 14: ...12 10 Care and maintenance 10 1 PANEL VISUAL INSPECTION AND REPLACEMENT...

Page 15: ...spect all cables to verify that connections are tight the cables are protected from direct sunlight and sited away from areas of water collection It is recommended to check the torque of terminal bolt...

Page 16: ...erial 11 Specification Module Series 60pcs 156 75 156 75mm Polycrystalline Silicon DOUBLE GLASS Module Dimensions mm Weight kg 1658 992 6 Max System Voltage VDC 1500 Max Series Fuse A 15 Electrical Pe...

Page 17: ...39 5 Max Power Current Imp A 9 36 9 44 9 52 9 60 9 67 9 75 Open Circuit Voltage Voc V 47 3 47 5 47 7 47 9 48 1 48 3 Short Circuit Current Isc A 10 05 10 06 10 07 10 08 10 09 10 10 12 Bypass diode and...

Page 18: ...urrent IF AV is higher than the maximum system current at the highest operating temperature of module The peak repetitive reverse voltage VRRM is higher than the maximum system voltage at the lowest o...

Reviews: