2.12. Please make sure that there is no gap between the insulating gaskets of the joint. The gap
between the insulating gaskets may cause the fire and electric shock risk.
2.13. Please make sure that the polarity of each module or string is not the opposite with that of
other module or string.
2.14. Please don't artificially gather sunlight on these solar modules.
2.15. Under normal circumstances, the current and voltage generated by PV modules maybe
higher than those reported under standard test conditions on certain conditions.
3.Unpacking and storage
3.1. Please keep all components and electrical connections clean and dry before starting the
installation.
3.2. If a temporary storage module is required, a dry and ventilated room shall be used.
3.3. When unpacking, the modules shall be handled by both hands. Don't place the modules in
an overlapping mode.
3.4. The double glass modules should be carefully handled, and it is required to use slip-proof
gloves in the process of handling and installation.
3.5. Please use the supportive with disassembly tools when disassembling the plywood case.
4.Product identification
It is recommended to record the unique serial number of each module.
5.Environmentalconditionsandsiteselection
5.1 Weather conditions
The installation of ZNSHINE SOLAR AUSTRALIA PTY LTD. crystal series modules
should be carried out under the following conditions:
Environment temperature: -40 °C to +40°C
Working temperature: -40 °C to +85°C
Storage temperature: -20 °C to +40°C
Humidity: less than 85RH%
※The mechanical load capacity of module (including wind force and snowfall load) depends on