7
1.3.6 Connection of condensation drainage
The drainage is gravitational using Ø32 piping (not supplied) fitted with a
siphon system
with a purge cap
.
Condensation drainage,
from the front face the drainage is:
on the right if drainage from the rear, but can be switched to the left,
to do this:
- unscrew joint
from joint
,
- unscrew joint
from elbow
.
- reassemble on the other side making sure it is watertight (adjust
the length of the flexible tube to avoid pinching it).
on the side opposite the drainage if it is lateral.
For placing the condensation drainage: see mark “A Ø26/34“
§ “dimensions” in the appendix.
1.3.7 Electric connections
1.3.7.1 Voltage and protection
The electrical supply must be provided through a protection and circuit breaking device (not
supplied) complying with the standards and regulations in force in the country where it is installed (in
France standard NF C 15100).
Electrical protection: 30 mA ground fault circuit breaker (at the head of the line).
Acceptable voltage variation tolerance: ± 10% (during operation),
Electric cables must be fixed.
Prior to any operation, check that the voltage on the identification plate of the
appliance corresponds to the mains voltage available on site.
Pool
*minimum distance
CAE 508-510-513
suction grid
blowing grids + connector box
Hygro Control
fresh air intake
air renewal system (see §1.3.2)
duct exhaust
suction
blowing
Technical room
Swimming
pool
hall
To the drain
Summary of Contents for CAE
Page 22: ...1 Sch ma lectrique Sch ma de puissance CAE 508 510 513...
Page 23: ...2 Sch ma de commande CAE 508 510 513...
Page 25: ...4 Dimensions weight without option Kg CAE 508 228 CAE 510 235 CAE 513 240...
Page 26: ...N o t e s N o t e n A a n t e k e n i n g N o t a s N o t a...
Page 27: ...N o t e s N o t e n A a n t e k e n i n g N o t a s N o t a...