Page 9
ENGLISH
Zodiac
®
Sheer Descent
®
and Fiberfall
®
Water Features
|
Installation and Operation Manual
Figure 3. Excavation and Steel Installation
4½" wide x 4½"
deep notch
Finished notch in beam
Steel off set
Top of raised bond beam
Note: Notching of the bond beam is the next
step in the process. The change to the
steel will make the notch a simple procedure.
3½"
on each side of the Sheer Descent unit). For FiberFalls,
offset the steel for the unit length plus 6 inches (15.2
cm) on the left to accommodate the lens chamber and
fiber cable, or 6 inches (15.2 cm) on both sides for
double-chambered units. See Figure 3.
2.3 Concrete Installation and
Modifications
For Sheer Descent, notch the bond beam 4-1/2 inches
(11.4 cm) deep and 1 inch (2.5 cm) longer than the
width of the unit. For FiberFalls, notch for unit length
plus 6 inches (15.2 cm) on the left to accommodate the
lens chamber and fiber cable, or 6 inches (15.2 cm) on
both sides for double-chambered units. FiberFall also
requires a 1 inch (2.5 cm) conduit stub-up in the beam
for the fiber cable(s). See Figure 4.
For vinyl and fiberglass pools, configure block to match
gunite beam installation.
After notching the beam (setting blocks), do the
following steps: (Refer to Figure 5.)
1. Determine waterfall installation level with bender
board.
2. Tack bender board at notch 1-3/8 inches (3.5 cm)
below bottom of coping.
3. Cement back of board.
Figure 4. Concrete Installation
Unit Length Plus 1"
4-1/2"
Bond
Beam
Unit Length Plus 6" to Left
4-1/2"
Lens Chamber
with Cable
Bond
Beam
FiberFall
Sheer Descent
Bond Beam
Bender
Board
1-3/8”
Bender
Board
Cement
Figure 5. Install Bender Board