ZXR10 T8000 Hardware Installation Guide (Cluster)
No.
Check Items
Checking Method
3
Whether the expansion bolt fits the installation holes of the base
bracket and support leg;
Whether the bracket and the ground are insulated;
Whether the floor holder and guide rail are insulated
Set the multimeter to measure
the resistance value of the
insulated positions between
bracket and cabinet; the values
should be over 5 MΩ
4
Whether the installation of accessories such as the cabinet front and
rear doors is complete;
Whether the connection plate is installed in the case of side-by-side
cabinet installation
On-site check
5
Whether the cabinet front and rear doors can be easily opened and
closed
Manually open and close
cabinet doors
6
Whether the cabinets are arranged in neat rows. The cabinets on the
main aisle side should be lined up and the deviation should be less
than 5 mm
On-site check
7
Whether the board can be easily plugged/unplugged;
Whether the bolts on the board panel are securely installed and
whether the spring steel wire is intact
Check bolts and boards
8
Whether the equipment is clean and tidy. Cabinet parts should not be
deformed;
Whether various labels are correct, clear, and complete
On-site check
9
Whether the cabinet is clean. No dust should exist in the cabinet;
There should not exist redundant cable ties, cables or sundries in
the cabinet
On-site check
10
Whether antistatic wrist strap is inserted in the antistatic jack on the
cabinet
On-site check
11
Whether dummy panels are installed in idle slots
On-site check
12
The two circuit breakers of the equipment power distribution box
should be shut off before equipment power-on. The circuit breakers of
the power supply module should be turned on before the equipment
power-on for the first time. Use a multimeter to check whether
short circuit exists at various input terminals. If short circuit exists,
troubleshoot the problem before moving on to the next step.
If there is no problem with the tests described above, shut off the circuit
breaker of power supply module. Turn on the circuit breakers of the
equipment power distribution box first; then turn on the circuit breaker
of the power supply module to provide power for the equipment
On-site check and
measurement by multimeter
5-2