Installation tips
The CAN connection between the ZVM-GATEWAY and devices can also function as a power supply, and not
only for sending data. The distance between the ZVM-GATEWAY and the chargers should be less than 10
meters, otherwise another 12-24V power supply unit is required as an additional external power supply.
The standard installation is mounting to an indoor wall. If the system needs to be installed outdoors,
additional weather protection is required, as the device has a protection class of IP21.
9.4.2.
Installation materials
Number
Specifications
Quantity
Network cable
Shielded network cable, Cat. 5
As required
Network cable connector
RJ45
As required
Cable ties
4 x 200 mm
As required
9.4.3.
ZVM-GATEWAY positioning
In accordance with the project, route the power and communication cables to the location of the ZVM-
GATEWAY.
Follow the instructions in this manual regarding the connection of multiple chargers to the same ZVM-
GATEWAY. The standard installation is mounting to an indoor wall; the reference dimensions for
positioning the supports are shown in