18
Z886 PERMA-TRENCH
INSTALLATION INSTRUCTIONS
Z886 Sidewall Concrete Pour
FULL CHANNEL INSTALL WITH HEAVY-DUTY FRAME
1
Set the channel to the correct height.
2
Install reinforcing per bracing schedule
(bracing provided by others).
4
Remove internal sidewall bracing.
3
Using the standard concrete pouring method,
pour concrete so it is about 8" [204] from the top
of the trench.
5
Pour the remaining concrete, remove shipping/
installation bars, and use standard finishing practices
to finish the concrete.
POUR 1
POUR 2
6.25 [159]
4 [102]
MIN.
4 [102]
8 [203]