1
DEH40229 - Installation Instructions
PowerMark Plus
™ Load Centers
100
–
225 Ampere Single- and Three-Phase 10
–
42 Circuit
Rainproof Type
WARNING: Hazard of electrical shock or burn. Turn off
power before working inside this equipment.
General
To comply with the Canadian Electrical Code and the Canadian
Standards Association, the load center must be installed in
accordance with the information included on the label on the
inside of the equipment. This must also be done in accordance
with the applicable local electrical codes and by a qualified
electrical contractor or licensed electrician. For troubleshooting
or service related questions,
https://electrification.us.abb.com/products/load-centers
Installation
1. Remove the Door
Back out the door hinges. Remove the door and slip it back into
the carton to protect the finish. Save the screws for reuse.
2. Remove the Shield
a.
Loosen the fastening screw (the screw will be retained in the
shield).
b.
Insert a screwdriver under the loop, then lift the shield up
and out.
c.
Slip the shield back into the carton to protect the finish.
3. Remove the Service Entrance Barrier (Main Breaker only)
Back out and save the mounting screw securing the service
entrance barrier over the main breaker connections, then lift the
barrier up and out.
4. Remove the Interior (Optional)
Back out the mounting screws and save them for reuse.
5. For Top Feed, Screw the Hub (Not Included) onto the
Installed Conduit
Raintight hubs can be installed in any of the four positions
indicated below.
6. Fasten the Hub or Closing Cap to the Box
Attach the hub with the four screws supplied with the kit. No
gasket is required. If a hub is not used, attach the supplied closing
cap with the four screws in the kit.
7. Mount the Box
Screw or nail through the rear mounting holes.
Barrier
Mounting
Screw
Mounting
Screws