 GENERAL 

 
1.1

 

SUMMARY 
A.

 

This section includes packaged, factory-fabricated and assembled, gas-fired, three pass 
condensing firetube boilers, trim, and accessories for generating hot water for pressure as 
noted on plans. 
1.

 

Three pass firetube condensing boiler 

2.

 

Burner - Specify Fuel: Natural Gas, LP Gas or Combination Gas/#2 Oil 

 

1.2

 

SUBMITTALS 
A.

 

Product Data: Include performance data, operating characteristics, furnished specialties, 
and accessories. 
 

B.

 

Shop Drawings: For boilers, boiler trim, and accessories; Include plans, elevations, sections, 
details, and attachments to other work. 
1.

 

Wiring Diagrams: Power, signal, and control wiring. 

2.

 

Fuel Train Schematic 

 

1.3

 

CLOSEOUT SUBMITTALS 
A.

 

Operation and Maintenance Data: For boilers, components, and accessories to include in 
emergency, operation and maintenance manuals. 
 

B.

 

Warranties: As specified in this section. 

 

1.4

 

QUALITY ASSURANCE 
A.

 

Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, 
Article 100, by a testing agency acceptable to authorities having jurisdiction. 
 

B.

 

ASME Compliance: Fabricate and label boilers to comply with ASME Section IV Boiler and 
Pressure Vessel Code. 

 

C.

 

ASHRAE/IESA 90.1 Compliance: Boilers shall have minimum efficiency according to: Gas and 
Oil Fired Boilers 

 

Minimum Efficiency Requirements.”

 

 

D.

 

UL Compliance: Control devises and control sequences according to requirements of UL.  

 

E.

 

CSD-1 Compliance: Boilers/burners equipped to meet current state code. 

 

Summary of Contents for A3C-1000

Page 1: ...ions details and attachments to other work 1 Wiring Diagrams Power signal and control wiring 2 Fuel Train Schematic 1 3 CLOSEOUT SUBMITTALS A Operation and Maintenance Data For boilers components and accessories to include in emergency operation and maintenance manuals B Warranties As specified in this section 1 4 QUALITY ASSURANCE A Electrical Components Devices and Accessories Listed and labeled...

Page 2: ...BE CONDENSING BOILER A Basis of Design Product Subject to compliance with requirements provide products as listed 1 Aldrich Company Manufactured in Wyoming IL Model A3C B The boiler must be manufactured by a company having at least ten 10 years documented boiler manufacturing experience in accordance to ASME Section IV Boiler and Pressure Vessel Code C Description Factory packaged and firetested f...

Page 3: ...an 18 gauge steel jacket K Water Capacity The boiler must be of a high mass large volume design as listed below Gas Input BTUH Minimum Water Capacity Gallons 1 000 000 113 1 500 000 113 2 000 000 148 2 500 000 215 3 000 000 215 4 000 000 280 5 000 000 320 6 000 000 440 L Include the following 1 Handholes or inspection tappings for water side inspection 2 Lifting lug on to of boiler 3 Minimum 1 boi...

Page 4: ... driven by motor H Gas Train Control devices shall comply with requirements in ASME CSD 1 and UL Gas train to include pilot shut off valve regulator pilot solenoid valve intermittent electric spark pilot ignition with 100 percent main valve and pilot safety shutoff with electronic ultra violet supervision of burner flame flame rod not acceptable I Main Gas Train Factory piped and wired may be remo...

Page 5: ...ired by code 3 Construct concrete bases 4 high and extend base not less than 6 in all directions beyond the maximum dimensions of boiler unless otherwise indicated C Install gas fired boilers according to NFPA 54 D Install electrical devices furnished with boiler but not specified to be factory mounted D Refer to drawings for additional requirements 3 3 START UP SERVICE A The mechanical contractor...