S1500E Open Cooling Towers

XES1500E Open Cooling Tower

RIGGING AND INSTALLATION INSTRUCTIONS

RS1500Ev02EN

Summary of Contents for S1500E

Page 1: ...S1500E Open Cooling Towers XES1500E Open Cooling Tower RIGGING AND INSTALLATION INSTRUCTIONS RS1500Ev02EN...

Page 2: ...cated on the unit nameplate Recommended Maintenance and Monitoring Programme Checks and Adjustments Start Up Weekly Monthly Quarterly Every 6 Months Annually Shutdown Hot water basin X X Nozzles X X C...

Page 3: ...s on applied code of practice Notes 1 Water Treatment and auxiliary equipment integrated in the cooling system may require additions to the table above Contact suppliers for recommended actions and th...

Page 4: ...faces 9 Modifications by others 10 Warranty 10 2 Rigging 11 General Notes 11 Rigging Information 11 Rigging Method for Upper Section fully Assembled Unit 13 Rigging Method for Lower Section 13 Rigging...

Page 5: ...18 07x are shipped in one single section All other S15E models are shipped in two sections upper and lower due to shipping height restrictions For the dimensions and weights of a specific unit or sect...

Page 6: ...dware and accessory items At temperatures below 10 C the butyl sealer tape might loose it s flexibility We recommend to store the sealer tape in a heated room before using it during rigging at freezin...

Page 7: ...t the lifting devices should be used in conjunction with safety slings placed under the unit Anchoring The unit must be properly anchored in place Refer to the suggested support details on the certifi...

Page 8: ...e is doubt about safe and proper rigging installation operation or maintenance procedures contact the equipment manufacturer or his representative for advice When working on operating equipment be awa...

Page 9: ...d as far away as possible from occupied areas open windows or air intakes to buildings Caution EACH UNIT SHOULD BE LOCATED AND POSITIONED TO PREVENT THE INTRODUCTION OF DISCHARGE AIR INTO THE VENTILAT...

Page 10: ...all products to be free from manufactured defects in materials and workmanship for a period of 12 months from the date of shipment In the event of any such defect BAC will repair or provide a replace...

Page 11: ...ifts or where hazards exist it is recommended to use the lifting devices in conjunction with safety slings placed under the unit 4 The proper rigging sequence for units is to lift the lower section in...

Page 12: ...3000 1350 2700 B 3000 1500 2700 C 3000 1500 5200 S15E XES15E 1212 07x FULLY ASSEMBLED A 3600 1800 3700 S15E XES15E 1212 09x 1 1 A 3600 1800 2700 B 3600 1700 2100 C 3600 1800 4600 S15E XES15E 1212 10x...

Page 13: ...Section fully Assembled Unit RIGGING METHOD A 1 Lifting cable 2 Lifting ears Rigging Method for Lower Section RIGGING METHOD B 1 Lifting cable 2 Lifting ears W W W B A L T I M O R E A I R C O I L E U...

Page 14: ...n the lower section For units boxsize 08x09 08x12 10x12 12x12 pay attnetin to the difference in lifting ear and tie down buckle on the fan side of the unit opposite to air intake The lifting ear is to...

Page 15: ...tie down buckle and Lifting ear on lower section 1 Proper use of Tie down buckle is shown on logo 2 Proper use of Lifting ear is shown on logo W W W B A L T I M O R E A I R C O I L E U 15 2 Rigging 2...

Page 16: ...l sealer tape supplied with the unit on the mating flanges of the lower section in a continuous line over the centre line of the tapper holes At each corner allow 2 to 3 cm overlap Do not stretch seal...

Page 17: ...l holes from upper section and lower section are properly aligned before lowering the top section completely to the bottom section Position of the fastening holes to be used 1 Fastening hole 2 Drift p...

Page 18: ...sories 3 Sealing methods are the same as for the upper section 4 The platform ladder and railing is packed on a separate skid The assembly hardware is packed in a plastic container and strapped to the...

Page 19: ...Clean out port cover mounted for transport Final installation of clean out port cover W W W B A L T I M O R E A I R C O I L E U 19 4 Optional Accessories Assembly 4 Optional Accessories Assembly...

Page 20: ...ng and Maintenance Manual see Table Recommended Maintenance and Monitoring Programme on page 2 must be performed Proper start up procedures and scheduled periodic maintenance will prolong the life of...

Page 21: ...cific assistance at www BaltimoreAircoil eu More Information REFERENCE LITERATURE Eurovent 9 5 6 Recommended Code of Practice to keep your Cooling System efficient and safe Eurovent Cecomaf 2002 30p G...

Page 22: ...W W W B A L T I M O R E A I R C O I L E U 22...

Page 23: ...W W W B A L T I M O R E A I R C O I L E U...

Page 24: ...W W W B A L T I M O R E A I R C O I L E U...

Page 25: ...W W W B A L T I M O R E A I R C O I L E U...

Page 26: ...W W W B A L T I M O R E A I R C O I L E U...

Page 27: ...W W W B A L T I M O R E A I R C O I L E U...

Page 28: ...VE CONDENSERS HYBRID PRODUCTS PARTS SERVICES www BaltimoreAircoil eu info BaltimoreAircoil eu www balticare com info balticare com Please refer to our website for local contact details Industriepark Z...