ABOUT THIS MANUAL

This manual explains the installation, operation and maintenance of 

the Badger Meter® MEASURE RITE® sight tube assembly. 

UNPACKING AND INSPECTION

To avoid damage in transit, MEASURE RITE truck meters are shipped 

to the customer in special shipping containers. 

OTEE:

N

If damage to a shipping container is evident upon receipt of a 

meter, request the carrier to be present when the meter  

is unpacked.

Retain the container and all packing material for possible use in 

reshipment or storage. Visually inspect the meter and applicable 

accessory device for any physical damage. If damage is found, 

immediately notify carrier for insurance purposes.

INTRODUCTION

The Badger Meter MEASURE RITE Sight Tube tank level indicator 

is used in admix dispenser systems that are mounted on the side 

of Badger Meter stainless steel ASME certified tanks. However, the 

unit may be used in additional level-indicating applications if the 

material is compatible and within the pressure rating.

SPECIFICATIONS

Pressure

Since the pressure rating of the SST ASME tanks and associated 

system is 100 psig, this assembly is also rated for 100 psig at 75° F. 

However, in other applications, this unit may be suitable for higher 

pressures. Consult the factory for more information.

Temperature Range

Optimum Temperature Range: 40…120° F. With care of the sight 

tube, and as long as the fluid does not freeze, the unit can be used 

down to 30° F.

INSTALLATION OF TANK FITTINGS

1.  Thread the 1/2" NPT of the upper fitting onto the tank fitting, 

leaving the opening for the sight tube at approximately the  

5 o'clock position. This will allow the tube to be inserted, then 

the fitting is rotated to the 6 o'clock position for insertion into 

the lower fitting. 

OTEE:

N

Depending on the tube length, and since the fittings  allow 

for some misalignment, the tube may be installed or 

removed with both fittings facing each other.

2.  Install pipe plugs in unused openings.
3.  Install the lower fitting, aligning the tube opening parallel with 

the tank (pointed toward the upper fitting).

4.  Remove the stop plug. The stop plug should be connected to 

the upper fitting using the provided ball chain and 5-40 screws.

5.  Measure the distance "X" between the fittings.
6.  Add 1-3/8" to the "X" dimension. Length tolerance is 

+0.00/ –0.032".

7. Measure and cut the Clear 

Schedule 80 PVC Pipe, keeping 

the cut square relative to the 

pipe sides.

8. Use a file or small knife to deburr 

the inside of the pipe ends and 

slightly chamfer (angle) the ends 

of the pipe so they will slip past 

the O-rings without damaging 

them.

9. Lubricate the O-Rings with 

silicone grease and insert them 

into each fitting groove.

OTEE:

N

Silicone lubricants may be 

ordered from Badger Meter 

or obtained locally. Two 

suitable silicone lubricants are available in stock: 

P/N 258238-0001 – High viscosity silicone oil  

P/N 500458-0021 – Silcone grease

10. Carefully insert the tube up through the o-ring of the upper 

fitting, until it stops.

11. Rotate the upper fitting from the 5 o'clock position to the 

6 o'clock position, aligning the opening with the opening in the 

lower fitting.

12. Slide the tube down into the lower fitting until it stops. The fit 

should be snug.

13. Once the tube is seated, install the stop plug. The plug prevents 

the tube from slipping upward during use or during handling.

14. Use thread-sealing compound or TFE tape on all pipe fittings.
15. Normally, NPT fittings require only 2-3 turns past hand tight.
16. Replace any plastic pipe plugs before pressurizing, with

 

either a bypass valve or metal pipe plug.

OTEE:

N

Bottom fitting is available with side or bottom drain fitting. 

Specify when ordering. Drawing depicts both.

DO NOT USE A METAL SCREWDRIVER TO REMOVE OLD O-RINGS, 

AS THIS MAY DAMAGE THE O-RING SEALING SURFACE. USE 

PLASTIC OR WOOD.

THE UPPER AND LOWER FITTING MUST BE RIGIDLY FIXED, TO 

PREVENT SEPARATION, BY MAKING SURE THE CONNECTING 

PIPING WILL NOT ALLOW MOVEMENT. DO NOT CONNECT TO 

PLASTIC FITTING.

PVC PIPE IS NOT RECOMMENDED FOR STORAGE OR 

TRANSPORTATION OF COMPRESSED GASES. LIMIT THE 

DURATION OF PURGE-GAS PRESSURE TO NO MORE THAN 5 

MINUTES. NEVER LEAVE GAS PRESSURE ON TANK/ SIGHT TUBE 

ASSEMBLY FOR EXTENDED PERIODS. NEVER REMOVE, BLOCK OR 

ADJUST SAFETY RELIEF VALVES TO PRESSURES HIGHER THAN 

FACTORY SETTINGS.

MEASURE RITE®

Sight Tube Assembly 

CON-UM-01323-EN-02 (March 2015)

User Manual

Jamieson Equipment Company

www.jamiesonequipment.com

toll free 800.875.0280