INSTRUCTIONS FOR THERMOWELD GROUNDING CONNECTIONS - CABLE TO BUS BAR

CB-26

Place cable and bus bar into mold.

CB-32

Place cable into mold and then 

butt bus bar against cable.

CB-28

Place bus bar in the mold as 

shown.  Position cable into mold 

until the end is even with the 

center of the tap hole.

CB-15

Place bus bar in the mold with end of the bus bar at the 

center of the tap hole.  Place cable into mold until end 

is butted against the bar.  After weld 

is complete, open mold.  One side will 

swing open away from 

bus bar.  Now slide 

mold down 

bus bar until 

mold is clear 

of weld and 

then lift mold 

up off of bus 

bar.

CB-33

Place lug in mold and butt cable 

up against lug under center of 

tap hole.

CB-23 & CB-24

Place bus bar in the mold as 

shown then butt end of cable 

against bus bar.

CB-24

CB-23