background image

INSTALLATION GUIDE

canusacps.com

SIS Sa 2½

near white metal

SSPC SP 10

Ensure that the pipe is dry before cleaning. 
Thoroughly clean the weld area with a sand or 
grit blaster to “near white metal” SIS Sa 2½ or 
equivalent. Using a grinder with a grind disk 
with roughness rating of 40-60, ensure that 
the PP mainline coating edges are beveled to 
15° from the horizontal and that the adjacent 
PP pipe coating is cleaned, exposing fresh 
PP, to a distance of 25mm beyond the sleeve 
width.

25mm + Slee

ve

 Width + 25mm

GTS-PE

4

Factory Grade 3LPE Field Applied Coating System

12

Place the underlap of the sleeve onto the joint, 
centering the sleeve such that the sleeve 
overlap is positioned at either the 10 or 2 
o’clock position. Press the underlap fi rmly into 
place and use a roller to work out any trapped 
air. Feed the remaining length of sleeve under 
the pipe. 

Optional Heat Shields can be used during the 
sleeve application. After wrapping the sleeve 
around the pipe, the heat shields can be 
wrapped adjacent to the sleeve to protect the 
mainline coating during shrink down.

Equipment List

2

1

GTS-PE Global Transmission Sleeves are 
shipped pre-cut with a preattached closure. 
Bulk quantities are also available. The joint 
completion system uses liquid epoxy on 
bare steel cutback. The GTS-PE sleeves are 
packaged in PE bags that are only to be opened 
prior to the application of the product.

Product Description

Propane tank, hose, torch & regulator; Power 
grinder with grind wheel of a Grade 40 grit 
rating; Canusa heat shields, Induction coil & 
generator; Digital thermometer with suitable 
probe; Knife, J roller, rags & approved solvent 
cleanser; Standard safety equipment; gloves, 
goggles, hard hat, etc.

Flame Intensity & Torch Size

Pipe O.D.

≤ 450mm 

   (18”)     

Minimum Torch Size:
150,000 BTU/hr. 

Minimum Torch Size:
300,000 BTU/hr. 

Use 

moderate to high

 

fl ame intensity or 
induction heating for 
metal cutback pre-
heating and shrinking.

Use 

moderate

 

fl ame intensity or 
induction heating for 
metal cutback pre-
heating and shrinking.

Pipe O.D.

> 450mm 

   (18”)     

3

Canusa recommends the use of induction 
or infrared heating equipment for pipe sizes 
greater than 760mm(30”) O.D.

9

Liquid Epoxy Application

Apply mixed epoxy to a minimum uniform 
thickness of 6 mils (150 microns) on all 
exposed bare metal plus FBE toe only, using 
the applicator pads as supplied or an approved 
tool.

11

Check the temperature to ensure the preheat 
has been obtained on the entire pipe circum-
ference.

 This preheat will substantially cure the 

epoxy and ensure proper fl ow and bonding of 
the sleeve adhesive. Ensure that the epoxy is 
dry to the touch prior to sleeve installation.

Sleeve Installation

Pre-Heat

Preheat the epoxy to a minimum of 130°C 
using the appropriate sized induction coil. While 
induction heating is highly recommended, in 
certain cases, propane torches may be used if 
proven to provide acceptable results in project 
specifi 

c conditions. Preheat temperature 

and profi le is dependant on project specifi c 
conditions, and must be determined prior to 
the start of the project.

10

> 130°C

> 130°C

(> 266°F)

(> 266°F)

GTS-PE Sleeve

Epoxy BP

Cure

Base

8

Liquid Epoxy

Follow the preparation, mixing and applications 
instructions provided with the supplied Canusa 
Liquid Epoxy Pack.  For bulk quantities, mix 
the epoxy cure with epoxy base (see Liquid 
Epoxy Product data sheet for mixing ratio). Stir 
for a minimum of 1 minute to assure uniform 
mixture.

Epoxy CB

Epoxy BP

Base

Base

Cure

Cure

Positional Markings

Measure and mark the width of the GTS-PE 
sleeve across the joint. Also, adjust the induc-
tion coil’s heating area to the width of the 
GTS-PE sleeve. The induction coil heating 
width shall be approximately 25 to 75 mm 
wider than the supplied GTS-PE sleeve width.

6

5

Wipe clean or air blast the steel and pipe 
coating to remove foreign contaminants.

Pre-Warm

Using the appropriate sized induction coil or 
propane torch, pre-warm the steel area to 
50-65°C. Using a temperature measuring 
device, ensure that the correct temperature is 
reached on the steel.

7

50°C-65°C

(122°F-149°F)

C

C

)

Reviews: