background image

 

INSTALLATION MANUAL 

Absorption Chiller 

16LJ-F Series 

 

 

 

 
 

Original language 

ACQA36-00270 

 

Summary of Contents for 16LJ-F Series

Page 1: ...INSTALLATION MANUAL Absorption Chiller 16LJ F Series Original language ACQA36 00270 ...

Page 2: ...ent of Declaration of conformity Statement for Equipment for witch Compliance with the Protection Requirements is not ensured in Residential Areas EMC Directive 2014 30 EU clause 9 4 This product must not be used in residential areas This product may cause interference if used in residential areas Such use must be avoided unless the user takes special measures to reduce electromagnetic emissions t...

Page 3: ...ling work 4 2 4 Procedure and note for horizontal pulling installation 4 2 5 Installation location 4 2 6 Installation space 4 2 7 Safety precautions at the installation on the foundation 5 3 Requirements for the foundation 3 1 Foundation work 5 3 2 Accuracy of dimensions and levelness of the foundation 5 3 3 Foundation bolts 6 4 Piping 6 5 Field wiring 6 6 External visual inspection 6 ...

Page 4: ...g of the unit shall be done by the licensed professionals following the manufacturer s instructions Inappropriate operation may cause accidents such as turnover falling etc Unit shall be firmly fixed Unit shall be firmly fixed by bolts nuts on the foundation which has adequate strength to carry the system Strength poverty or fixing defect may cause a water leakage and or turnover of the unit in ca...

Page 5: ...unding works Grounding works is necessary but never connect the earth wire to the gas piping water piping and or earth line of the lightning rod or telephone Imperfect grounding may damage the unit or cause a shock Wires shall be securely connected Wires shall be securely connected and the terminal connection shall be stress free from any external force Defective connection may cause heat generati...

Page 6: ...is FOB shipping point Unloading horizontal pulling and setting are scope of supply for the purchaser 2 2 Rigging work and safety precautions 1 Only the licensee shall perform the rigging work 2 Confirm the Load and center of gravity on the specification 3 Rigging wire and shackle shall meet the local rule 4 Sling angle shall be within 60 degree 5 Four point suspension is essential Two point suspen...

Page 7: ...the unit shall be pulled ahead and behind 2 5 Installation location 1 Set the chiller on a firm and flat floor 2 The installation location should be free from corrosive gas dust and high humidity 2 6 Installation space Ensure the space based on the external dimensions in the contract specification 1 Tube removal space To enable the replacement of the all heat transfer tubes the space must be secur...

Page 8: ...oise and vibration should be taken into consideration 3 2 Accuracy of dimensions and levelness of the foundation Important precaution for the foundation dimensions are flatness of each foundation and levelness error between two foundations parted in a longitudinal direction of the chiller Permissible levelness for the absorption chiller installation The permissible levelness for the absorption chi...

Page 9: ...tage categoryⅢ And other connections shall follow the overvoltage categoryⅡ Connect each wire according to CE requiring 2 Refer to Field electric wiring and Electric wiring diagram in the contract specifications for wiring connection 3 A properly qualified electrician should carry out the electrical wiring works 6 External visual inspection The followings shall be inspected 1 Insulation for the Ch...

Page 10: ...s 4 No looseness shall be observed at each Water header flange of the chiller 5 There shall be no liquid leakage from the Chiller 6 No damage shall be observed on all components of the Chiller 7 There shall be no missing of all components of the Chiller 8 No wire cut shall be observed on electric wiring and piping ...

Page 11: ...Manufacturer CARRIER SCS Route de Thil BP49 01122 MONTLUEL CEDEX FRANCE ...

Reviews: