background image

Static Uninterruptible Power Supply

 

Page 1 of 1 

Eaton 9390 Guide Specification 

October 9, 2009 

 

 

 

STATIC UNINTERRUPTIBLE POWER SUPPLY 

GUIDE SPECIFICATION 

Model Eaton 9390 20-160 kVA

 

 
PART 1 - GENERAL 

 
1.01 

SUMMARY 

 

A. 

This specification describes a three-phase continuous duty, on-line, double conversion, 
solid-state uninterruptible power system, hereafter referred to as the UPS.  The UPS 
shall operate in conjunction with the existing building electrical system to provide power 
conditioning, back-up and distribution for critical electrical loads.  The UPS shall consist 
of, as required by the project, the UPS module, battery cabinet(s), and accessory 
cabinet(s) for transformers, maintenance bypass, parallel tie, and distribution 
applications, and other features as described in this specification. 

 
 
1.02 

UPS SYSTEM DESCRIPTION 

 

A. 

UPS System Components:  The UPS system shall consist of the following main 
components: 

1. 

UPS module containing a Rectifier, Inverter, Battery Charger, Static Bypass, and 
associated Control and Monitor Panel. 

2. 

Battery string(s) in Line-and-Match Battery Cabinets. 

3. 

Line-and-Match accessory cabinets for transformer, maintenance bypass, 
parallel tie, and distribution applications. 

4. 

Non-matching wall mounted or floor standing maintenance bypass cabinets or 
multi-module parallel tie cabinets. 

 

B. 

UPS Module Modes of Operation:  The UPS Module shall operate as an on-line, fully 
automatic system in the following modes: 

1. 

Normal:  Utilizing commercial AC power, the critical load shall be continuously 
supplied by the Inverter.  The Inverter shall power the load while regulating both 
voltage and frequency.  The Rectifier shall derive power from the commercial AC 
source and shall supply DC power to the Inverter.  Simultaneously, the Battery 
Charger shall charge the battery. 

2. 

Battery:  Upon failure of the commercial AC power, the critical load shall continue 
to be supplied by the Inverter, which shall obtain power from the batteries without 
any operator intervention.  There shall be no interruption to the critical load upon 
failure or restoration of the commercial AC source. 

3. 

Recharge:  Upon restoration of the AC source, the Charger shall recharge the 
batteries and simultaneously the Rectifier shall provide power to the Inverter.  
This shall be an automatic function and shall cause no interruption to the critical 
load. 

4. 

Bypass:  If the UPS module must be taken out of the Normal mode for overload, 
load fault, or internal failures, the static bypass switch shall automatically transfer 
the critical load to the commercial AC power.  Return from Bypass mode to 
Normal mode of operation shall be automatic. No-break transfer to and from 
Bypass mode shall be capable of being initiated manually from the front panel. 

5. 

Energy Saver:  The UPS shall continuously monitor the voltage and frequency of 
the bypass source. When the source parameters are within acceptable limits, the 

Summary of Contents for Powerware 9390

Page 1: ...UPS Module shall operate as an on line fully automatic system in the following modes 1 Normal Utilizing commercial AC power the critical load shall be continuously supplied by the Inverter The Invert...

Page 2: ...EC 62040 1 1 International Electrotechnical Commission Uninterruptible power systems UPS Part 1 1 General and safety requirements for UPS used in operator access areas E IEC 62040 1 2 International El...

Page 3: ...f all field service offices must be submitted with the proposal Third party maintenance will not be accepted E Spare Parts Support Parts supplies shall be located in the field to provide 80 of all eme...

Page 4: ...nts the IGBTs from sourcing current in excess of their published ratings 3 An option shall be provided to allow the rectifier to be capable of operating from a delta transformer output or high impedan...

Page 5: ...onditions a Bypass voltage out of limits 10 of nominal b Bypass frequency out of limits 3 Hz adjustable factory set c Bypass out of synchronization d Bypass phase rotation installation error 6 Static...

Page 6: ...ocations 1 Rectifier charger input connections 3 wire plus ground 2 Bypass input connections 3 wire plus ground for 3 wire plus ground output configuration 480Vac or 4 wire plus ground for 4 wire plus...

Page 7: ...ll be removable from the front of the battery cabinet 4 Each battery cabinet shall feature a DC rated circuit breaker The circuit breaker within the battery cabinet shall only provide protection to th...

Page 8: ...VAC 3 wire plus ground for 3 wire plus ground output configuration 2 Operating input voltage range 10 15 of average nominal input voltage without battery discharge 3 For 60Hz systems operating input f...

Page 9: ...6 DC sensing Redundant DC voltage sensing methods shall be incorporated for providing battery over voltage protection 7 Battery charger characteristics The UPS battery charging system shall have the...

Page 10: ...le 11 Phase angle control a Balanced linear load shall be 1 degree from nominal 120 degrees b Unbalanced linear loads shall less than 5 degrees from average phase voltage for 100 load unbalance 12 Pha...

Page 11: ...e UPS shall withstand a 25 kV pulse without damage and with no disturbance or adverse effect to the critical load 11 Efficiency The UPS efficiency shall greater than 99 over the range of 10 to 100 loa...

Page 12: ...cessor controlled circuitry The UPS controls shall have the following design and operating characteristics 1 Fully automatic operation of the UPS shall be provided through the use of microprocessor co...

Page 13: ...tive cover which provides the following signals and communication features in a Class 2 environment 1 Alarm contact A dry contact for annunciating a summary alarm shall be provided for customer use Th...

Page 14: ...attended sequential shutdown of one or multiple computers powered by one UPS This shutdown shall be performed via in network or out of network means The order of shutdown shall be user defined allowin...

Page 15: ...ation operator training generator testing etc B The following procedures and tests shall be performed by Field Service personnel during the UPS startup 1 Visual Inspection a Visually inspect all equip...

Page 16: ...g service with monthly reports for UPS and battery performance Standard response time shall be 8 hours from receipt of call Manufacturer shall also offer as an option 7x24 on site service support with...

Reviews: