OSEP-2
Fluid Conditioning
System
Operation and
Maintenance
Instructions
Do not install or operate until you have read all
warnings and instructions and understand the
operation of this equipment.
• The OSEP-2 is not intended for and will not function
with solvent-based fluids. Using flammable or com-
bustible fluids will create a safety hazard.
• Read and follow all safety instructions supplied with
the coolant used in your machine tool or machining
center.
• Ensure that all fittings and connections are properly
tightened.
• Be sure that there are no bends or kinks in the fluid
return hose back to the tank. A blockage in the fluid
return line will cause the coalescing chamber to over-
flow.
Never work with equipment you feel may be
unsafe. Contact your Supervisor immediately.
INTRODUCTION
Upon receipt of the OSEP-2 immediately inspect the fil-
tration system for any damage that may have occurred
during shipping. The OSEP-2 is shipped completely
assembled and will only require minor adjustments and
connections to be completed for operation. The unit is
designed to continuously remove tramp oil and suspend-
ed solids.
SITE REQUIREMENTS
• The OSEP-2 requires a level area within ten feet of the
tank or sump it is servicing.
• The unit requires a space of approximately two feet (2')
by three feet (3'). This will allow access to the equip-
ment for service and inspection.
• Plant air with a maximum of 50 psi is also required to
operate unit. Position unit within reach of plant air.
• This equipment requires an air connection (maximum
pressure 50 psi) but does not require an independent
electrical power source.
• The system weighs approximately 170 pounds dry.
Once it is charged with aqueous coolant, it will weigh
approximately 300 pounds.
SET-UP AND INSTALLATION
• Remove OSEP-2 from skid by removing two of the
front wooden hold-downs.
For stationary installation, place next to machine tool
sump/tank and adjust threaded levelers accordingly.
795-90654
GM 04-01