Operators Manual
for
Capture Jet
®
Manual provides
Operation, Maintenance and Service Instructions
Form#: OM005_CAPTURE JET
Date: May 2017 - Rev2
Hoods
KVE (SJ-SK), KVC (SJ-SK), KVW (SJ-SK), KVL, KVM KVR, KVO AND KCH
Page 1: ...tors Manual for Capture Jet Manual provides Operation Maintenance and Service Instructions Form OM005_CAPTURE JET Date May 2017 Rev2 Capture Jet Hoods KVE SJ SK KVC SJ SK KVW SJ SK KVL KVM KVR KVO AND...
Page 2: ...contractor to see that the system installation is completed in accordance with the project plans and specifications and that it meets all specific requirements of local code officials The local author...
Page 3: ...to end or back to back see pg 8 for Installation of Splice Strips and U Channels 7 For hoods equipped with a supply fire damper it is very important to make sure that the fire damper is set in an open...
Page 4: ...he Capture Jet plenum on top of the hood or mounted in an electrical enclosure The submittal drawings will detail the location of the speed controller s Information regarding the fan and speed control...
Page 5: ...ew through top of flange to wall screw head will not interfere with hood Screw backsplash to wall or attach with adhesive Halton canopy hoods should be installed from 78 min 84 max above the finished...
Page 6: ...e top of the hood using the turnbuckles will make final adjustments easier Hanging height of Canopy hoods should be per local building codes verify with Authority Having Jurisdiction for hanging heigh...
Page 7: ...be attached to supply collar with sheet metal screws or pop rivets and sealed with duct tape Screws or Rivets are not to interfere with the operation of the fire damper if equipped Recommended Exhaust...
Page 8: ...upply plenum Fig 1 Fig 2 U Channel For hood models that are placed back to back as shown in Fig 1 Slide the U Channel A up over the back of the hood systems and secure with sheet metal screws For hood...
Page 9: ...nel and vertical flange on top of hood should line up 2 Hammer clips C over the two vertical flanges 3 Attach panels B to wall using appropriate hardware D 4 Slide front panel A into place 5 Attach pa...
Page 10: ...AT ANY TIME FANS WILL REMAIN ON FOR 15 MIN AFTER EXHAUST FAN SWITCH IS TURNED OFF H TR 15 MIN DELAY OFF TIMER N 1 2 TR 1 3 4 TEMP SENSORS C R1 R1 1 R2 7 8 R2 1 120V ADDITIONAL RELAY NOTE THE USE OF R...
Page 11: ...es in the fire suppression control cabinet Provision is also made for a Make Up Air interlock which can start the Make Up Air fan whenever the exhaust fan is operating This circuit is typically wired...
Page 12: ...NEUTRAL INCOMING CIRCUIT 120 1 60 J BOX J BOX BLACK WHITE BY HALTON FIELD WIRING The KVL external Capture Jet fan has a fire damper in the collar that must be set to open before the fan is attached to...
Page 13: ...ent screw The adjustment screw allows control of the fan and thus the amount of airflow from the Capture Jets 3 The Capture Jet fan should be adjusted to produce 0 25 of positive water column pressure...
Page 14: ...the cooking equipment is in operation to create a thermal plume prior to the air balancer to be able to use theT A B ports For accurate results the balance contractor should receive a copy of the job...
Page 15: ...and down Lift filter out of plenum Tilt top of filter out Lift filter into plenum Push filter in and down Tilt top of filter in Lift filter to the front Slide filter down Remove KFR tool To remove fi...
Page 16: ...andescent or Fluorescent lighting available KSA Filters 78 84 A F F Standard Verify with Authority in project location for min hanging height 16 ga duct work all welded per code Standard top mounted C...
Page 17: ...3 EN Model KVC Typical Installation Filtered MUA unit on the roof 40 min 120 min 16 ga duct work all welded per code Stainless Steel KSA filters Capture Jet air 78 84 A F F 78 Std Make up airflow Veri...
Page 18: ...r restaurant cooking appliances 78 84 A F F 78 Std Side view of typical install Integrated Capture Jet location 40 min S S KSA Filters Exhaust Air LED lights T A B Ports Integrated Capture Jet fan Ver...
Page 19: ...lation Capture Jet fan KSA filters LED lighting T A B Ports Exhaust Air S S Perf Low Velocity Supply Air W 2 Perf Plenum Capture Jet Air W 1 Perf Plenum Supply Air Exhaust Air Supply Air Capture Jet f...
Page 20: ...Model KVL Typical Installation UL listed upblast fan for restaurant cooking appliances 40 min 58 64 A F F Capture Jet fan Stainless Steel KSA filters 16 ga duct work all welded per code Capture Jet ai...
Page 21: ...Maintenance Manual OM 005 052017 rev3 EN Model KVM Typical Installation UL listed upblast fan for restaurant cooking appliances 40 min Capture Jet fan Stainless Steel KSA filters 16 ga duct work all w...
Page 22: ...1 Panels A are placed at the outside ends of the hood at each end of the hood group 2 Align the weld studs on the upper edges of the side skirts with the holes in the lower edge of hood ends and hang...
Page 23: ...lter angle 24 minimum height Model KVR Round and Oval hoods can be shipped in pieces for field assembly If pieces are shipped loose parts will be marked for easy assembly and an Operation and Installa...
Page 24: ...24 Capture Jet Operation Maintenance Manual OM 005 052017 rev3 EN Model KCH Typical Installation...
Page 25: ...p Date Product Serial Numbers Contact Information Contact Name Title Chef Kitchen Mgr Facility Mgr Property Mgr etc Facility Management Company Name if applicable Email Phone Number Cell Number Fax co...
Page 26: ...ied third party No claims for labor charges will be approved for payment if work commences without prior authorization by Halton Purchaser shall pay incurred premium labor charge including overtime we...