background image

1

FD80-AFH HEAVY DUTY ALUMINUM FRAME SLIDING DOOR
(Surface Mount Roller, Standard Sliding) Installation Manual

Part No.FD80HMP-AF

Thank you for selecting our product. Before starting installation, please read this manual thoroughly to ensure correct installation.
Please keep this manual at hand for future reference.

ABOUT THE PRODUCT

   

This product is a parts set for heavy duty aluminum frame sliding door 

system for indoor use.

SPECIFICATIONS

Without Intermediate

support

With Intermediate

support

Max.Door width

900 mm

1500 mm

Max.Door height

2200 mm

2500 mm

Min.Door thickness

5 mm or 6 mm

Max.Door weight

80 kg

Height adjustable range

4 mm upward, 4 mm dounward

FOR YOUR SAFE WORK AND CORRECT INSTALLATION

WARNING:

 

If these warnings are not followed, it may result in death or serious injury.

  

Caution:

If these cautions are not followed, it may result in injury or damage.

  

This (sliding door system) should be installed by an experienced person who has correct knowledge. If the system is not 
installed correctly, the door will not operate smoothly, and or may cause injury.

It is necessary to manufacture the frame with sufficient strength so it endures the weight of the door and impact shocks 
upon opening/closing the door. A frame with poor strength might result in improper and slower movement of the door. In 
the worst case, the door might drop down and cause injury.

Do not try to use this product for any other purposes other than originally intended for. Do not use the parts for applications 
that are out of specification.

Do not disassemble nor modify any parts than those described in this document.

Make sure to follow the designated measurements and specifications as well as horizontal and verticals angles. Make sure 
that the frame is not warped, since it may affect the movement of the door.

If cutting any parts, make sure to remove any burr before installation. Also check the upper track for any left-over burr or 
scrap and remove these.

This (sliding door system) is a part for architectural fittings. After installation, make sure to test the finished product 
thoroughly to ensure that it is well-functioning and safe.

Make sure to test the screws for slack at regular intervals (one month from first usage, half year and then one time every 
year is recommended).

To avoid damaging of aluminum frame, carry out installation work on clean floor.

Please use the tempered glass. It is recommended to use shatter-proof film on the glass.

 When installing “pocket door” specification, make “easy-maintenance” structure. For example, use removable panel. 

Prohibited

Warning
Caution

Required

Meaning of symbols

Summary of Contents for FD80-AFH

Page 1: ...ening closing the door A frame with poor strength might result in improper and slower movement of the door In the worst case the door might drop down and cause injury Do not try to use this product fo...

Page 2: ...ket countersunk head screw M4 x 25 8 pcs for Corner Part Horizontal frame 2000 mm Vertical frame 2500 mm 3000 mm Upper track Various sizes Accessory screw Pan head tapping screws 5 40 Gasket for 5 mm...

Page 3: ...00 19 60 18 32 2 5 5 additionaol When door jumb is not prorided apply Two way soft closer CAUTION 9 5 3 5 2 5 11 8 1 7 4 5 8 12 1 13 12 2 10 11 5 10 3 7 5 INSTALLATION DRAWING EXAMPLE 1 Height adjusta...

Page 4: ...r of glass panels GW Glass width DW 34 DH Door height FH 64 Cut off after the decimal point for the divided dimensions Example 2 Example 1 Ex 1 door on single track Size of each door when Opening widt...

Page 5: ...50 Thickness of Vertical frame x 2 1 3 Cutting and hole processing of Intermediate support when used Cut carefully so the cut edge is square to avoid bias and skewing Make sure to remove any burr Als...

Page 6: ...pth 20 mm 2 holes at each end 1 4 Processing of Vertical frame Step 1 1 5 Processing of Vertical frame Step 2 Drill holes according to the quantity of Intermediate support Hole A only if there is no I...

Page 7: ...into the track two Upper roller and Upper stopper in the order shown in below figure 2 Tape around rollers and upper track to prevent drop of inserted parts Installing Upper track and Floor guide S 3...

Page 8: ...ead screw M4 x 25 Hexagon socket head cap screw M6 x 30 Vertical frame 4 1 Preparation of Horizontal frame Upper Assembling door 4 Set the Bracket to upper Horizontal frame using Plate nut The distanc...

Page 9: ...50 Vertical length GH Glass height Glass Bottom side Glass Gasket Horizontal length DW Door width 50 Hexagon socket head cap screw M4 x 30 Intermediate support Bottom side 4 3 Insertion of glass Step...

Page 10: ...ngth DW Door width 50 Hexagon socket head cap screw M6 x 30 Corner part Horizontal frame upper Hexagon socket countersunk head screw M4 x 25 Top side Bottom side 4 5 Insertion of glass Step 2 when Int...

Page 11: ...er from shifting Top side Bottom side Spatel 4 7 Assembly of Vertical frame Bend the Edge cover between your fingers and press it into the side of the Vertical frame 4 8 Assembly of Edge covers You ma...

Page 12: ...be hanged Tilt the door as shown in the figure and set the Floor guide S to the groove of the bottom Horizontal frame 2 Push the door and set the hanger bolts as shown in the figure below 1 2 2 2 Be...

Page 13: ...lder as shown below 3 After adjusting the door pull the wrench at a right angle away from the door Make sure the width across flats of the bolt head is as shown in the figure Adjustment of door height...

Page 14: ...the track and pull out the roller Then clean the roller Check for loose screws retaining the upper track Tighten the screw Heavy door operation Check if door bottom contacts with floor Confirm that t...