Prepare for installation
Install hardware
Cable storage
Complete system setup
and configuration
1
2
3
4
DM7100H Systems
Installation and Setup Instructions
Prepare for installation
|
Stage
1
You provide
In the box
Pre-setup
1. Unpack all boxes and inventory contents.
2. Complete the Cluster Configuration Worksheet.
Screwdriver
Client
Runs the software to configure
your storage system.
Rack space
4U per DM7100H chassis
+4U for each DM600S shelf
or +2U for each DM240S shelf
or +2U for each DM120S shelf
Additional network cables
For connecting your storage system
to your network switch and
Microsoft® Windows® client
RJ-45 cables
Wrench port (e0M/BMC)
(order-dependent)
Storage Cables
mini-SAS HD to
mini-SAS HD cables
100 GbE cables (QSFP28)
25 GbE cables (SFP28)
HA interconnect, GbE network cables
32 Gb FC (SFP+ Op)
FC optical network cables
Additional cables
Power cables
Ethernet cables
micro USB console cable
Slide rail kit
Cable management tray
16 Gb FC or 25GbE cables
Mezzanine cards (SFPs pre-installed)