Page 4
EMERGENCY LIGHTING TESTING
Months 1 to 11 inclusive – Function Test, interrupt the permanent/UnSwitched supply and check the luminaire operates in Emergency
mode at reduced output
Month 12 (Annual) – As months 1 to 11 but for a full 3hr duration
Luminaire Ref / Location:
........................................
In Case of difficulty, contact the Installation Engineers:-
Tel: .........................................................
LHBCx11Exx/LHBCx22EXX
Duration 3hr
Lamp Type - LED
INITIAL USE AND ROUTINE TESTING
From initial install the downlight will require up to 24hr for the batteries to be fully charged and provide the rated 3hr duration
in Emergency mode. Then following subsequent Emergency use, from full discharge will take approx. 14hr to fully recharge batteries.
It is important that the luminaire is routinely tested to ensure the batteries are conditioned and also to fully comply with BS5266.
A function test should be conducted every month with an annual test of the full 3hr duration. Records can be kept on the adjacent table.
It is recommended that batteries are replaced every 4 years to ensure the optimum charging cycle is maintained.
Month
Test
1
Function
2
Function
3
Function
4
Function
5
Function
6
Function
7
Function
8
Function
9
Function
10
Function
11
Function
Annual
Full Test
Signed
Date
Fifth Year
Signed
Date
Fourth Year
Signed
Date
Third Year
Signed
Date
Second Year
Signed
Date
First Year
Page 1
Tech Help Line
UK -
0330 0249 279
Non UK -
+44 (0)1952 238 100
Supplied by LUCECO
Stafford Park 1, Telford,
Shropshire, England, TF3 3BD
Visit our website at
www.luceco.com
LHB.JH.04.2017
Tech Help Line
UK -
0330 0249 279
Non UK -
+44 (0)1952 238 100
Supplied by LUCECO
Stafford Park 1, Telford,
Shropshire, England, TF3 3BD
Visit our website at
www.luceco.com
LHB.JH.04.2017
SUGGESTED METHOD OF INSTALLATION
1. Identify a suitable location for installation.
2. Trunking:– This can be mounted using the central 20mm hole
(a)
For surface installation:– Use suitable fixing through fixing
points
(b)
3. The main housing is assembled to the bracket as shown.
Larger bolt and washers are used for main fixings.
Smaller bolt and washers are used for tilt adjustment slot
Installation & Operating Instructions
LED INDUSTRIAL
CERES HIGHBAY
IP65
RATED
1
WARRANTY
year
on site
5
WARRANTY
year
extended
NOTE – To comply with regulations, installation must be carried out by suitably
qualified competent person and in accordance with the current IEE Wiring
Regulations (BS7671) and Building Regulations. A copy of the instructions must
be left for the user/maintenance engineer for future reference.
For non-UK, please refer/consult local requirements
ENSURE ELECTRICAL SUPPLY IS DISCONNECTED/
ISOLATED BEFORE COMMENCING INSTALLATION
CRI
80
>
ASSEMBLY AND INSTALLATION
• Suitable for use with mains voltage 110-240V AC
• This product is pre-wired, with no user serviceable components.
Opening the luminaire may void the IP65 rating and warranty
Installation & Operating Instructions
UK ONLY
70,000
HOURS
100,000
HOURS
50,000
HOURS
STANDARD EXTRA
ULTRA
a
b
2
3