background image

 

 

 
 

 

 

 

NAF1000 CROSS-
CONNECTION 
CABINET 
INSTALLATION 
MANUAL

 

     

 

 

Summary of Contents for NAF1000

Page 1: ...NAF1000 CROSS CONNECTION CABINET INSTALLATION MANUAL ...

Page 2: ...sition the feet are adjusted so that the cabinet is in a straight position Make sure the cabinet is level It is a good idea to use the floor mounting kit that comes with the cabinet be sure that the cabinet is maintained in the right place If necessary the cabinet can also be mounted on the wall from the top of the cabinet with wall mounting kit The kit is an accessory ...

Page 3: ...ways 1 Splicing to the pigtail cables are done on a splice tray which is mounted on the splice tray holder inside the cross connection cabinet 2 Splicing to the pigtail cables are done on a splice tray which is mounted on the splice tray holder outside the cross connection cabinet 3 1 Installation of the splice tray holder inside the cross connection cabinet The splice tray holder is to be install...

Page 4: ...and splicing is carried out The splicing is done to the ready assembled NAF1000 pigtail cables The cables are brought into the cabinet in the following stages Release the lock at the bottom of the rotating frame and turn it completely open Pull the ends of the cables out from the bottom of the cabinet Pull the ends of the cables out of the cabinet over the cable peeling length which is about 250 c...

Page 5: ...or hot water If you are using a hot air fan be careful not to heat up the fiber tubes too much If there is an aluminum laminate or a corrugated steel sheet in the cable attach the earthing connector to the splitted sheet at the peeling point and pin the connector Protect the joint with an insulating tape 3 3 1 2 Central loose tube CLT cables Whittle the jacket off from both sides of the cable from...

Page 6: ...e of the central tube Cut the central tube of the cable at approximately 30 mm from the edge of the aluminum laminate or steel sheet and with a metal free cable at approximately 30 mm from the cable jacket Cut the central tube first making a transverse incision around the tube and then gently bending the tube on both sides until it breaks Pull the center tube off the fibers while holding the fiber...

Page 7: ...de of the tray then around the whole tray and finally from the right side to the splice protection sleeves The splice tray cover is inserted and marked with the necessary markings 3 5 Placement of splice trays mounted on the splice tray holder Pull the cable into the cabinet enough to leave the cable jacket outside the cabinet Temporarily attach the cable to the mounting points on the back of the ...

Page 8: ...erial number and length markings Insert the tail cable through the frame steering the cable into the cable guides on the right side of the rotating frame If you are installing multiple panels at the same time you can push the ends of the cables through the frame and cable guides at the same time Do not attach cables to the cable guides but try to leave them as loose as possible so that the panels ...

Page 9: ...cut off point Cut the cable to a suitable length Remove the splice tray from its holder and place it on the installation table Peel the cable and remove unnecessary wires and filling and center elements Attach the end of the tail cable to the opposite side with cable ties as the previously fastened Peel the fiber tubes to approx 6cm in length remove the gel If you are using Naficon s universal spl...

Page 10: ... cables place the cables in the correct position behind the frame and secure them with cable ties to the mounting plates on the bracket Connect the metal parts of the cables to the grounding rail on the rack Guide the fiber tubes in bundles behind the mounting plates and grounding rail from the hinge side of the rotating frame Attach fiber tube bundles behind the mounting plates Keep in mind the b...

Reviews: