background image

INSTALLATION AND

OPERATION MANUAL

Q.PEAK DUO L-G8.X solar module series

Valid for Africa, Europe, LatinAmerica, South America

Summary of Contents for Q.PEAK DUO L-G8 Series

Page 1: ...INSTALLATION AND OPERATION MANUAL Q PEAK DUO L G8 X solar module series Valid for Africa Europe LatinAmerica South America ...

Page 2: ...pment operational safety hazardous goods and environmental protection Regulations and requirements specific to the system Any applicable laws and requirements in particular inter national country specific regional laws and stipulations governing the planning installation and operation of solar power systems and work on roofs Any valid international national and regional regulations governing work ...

Page 3: ...OPERTY DAMAGE THIS INCLUDES IMPROPER INSTALLATION OR CONFIGURATION IMPROPER MAINTENANCE UNINTENDED USE AND UNAUTHORIZED MODIFICATION Fig 1 External dimensions in mm and components for Q PEAK DUO L G8 Q PEAK DUO L G8 3 1030 mm 1308 mm 2080 mm 35 mm 4 Mounting slots DETAIL A 8 Drainage holes 3 6 mm Frame DETAIL A 16 mm 8 5 mm 25 5 mm 979 mm DETAIL B 10 mm 7 mm 25 mm 4 Mounting slots system Tracker D...

Page 4: ...ply with any applicable laws and stipulations as well as with the following Conform to the necessary structural requirements Compliant with local snow and wind loads Properly fastened to the ground the roof or the façade Forces acting on the module are relayed to the mounting substructure Ensures sufficient rear ventilation of the module Avoid the usage of different metals to prevent contact corro...

Page 5: ...lity of the mounting system including clamps has to be evaluated by the system supplier The Q CELLS listed test load values were determinded with the following clamp parameters clamp width 40mm and clamp depth 10mm The system installer is responsible for the determination of location specific load requirements Ä Ä Ensure that the subconstruction does not touch the junction box even under load Ensu...

Page 6: ...verse currents caused by module defects ground leaks or defective insulation Ä Ä Ensure that the maximum reverse current load capacity indicated in the data sheet is met In order to limit reverse currents that may occur we recommend using the following safety options 1 Layout with a limited number of parallel connected strings Withoutundertakingfurthercurrentblockingmeasures amaximum of two module...

Page 7: ...ule damage may occur Ä Ä Never step on modules Ä Ä Do not subject modules to any mechanical stress Ä Ä Do not allow any objects to fall onto modules 3 INSTALLATION 3 1 SAFETY AND TRANSPORT Danger Risk of fatal injury due to electric shock Ä Ä Block off the installation zone Ä Ä Keep children and unauthorized individuals away from the solar power system Danger Risk of fatal injury due to electric s...

Page 8: ...m the separation of a closed circuit These can result in life threatening injuries The danger increases when several modules are connected in series Ä Ä Please be aware of that the entire open circuit voltage is active even at low levels of solar irradiation Ä Ä Pleasefollowthevalidnationalregulationsandsafetyguidelines for the installation of electrical devices and systems Ä Ä Please make sure to...

Page 9: ...es proceed in reverse order Danger Risk of fatal injury due to electric shock Ä Ä Electrical work may only be performed by qualified and skilled personnel see page 3 Ä Ä Ensure correct polarity Ä Ä Use solar cables for the connection at the junction box outlet Ä Ä Use the same inverter compatible plugs Ä Ä Use minimum 4mm2 copper wires insulated for a minimum of 90 C for field connections Note Mod...

Page 10: ...ry regulations Functional grounding For installations located in tropic regions between 23 5 N and 23 5 S with a module tilt of 5 functional grounding at the negative generator connection on the DC side must be implemented Ä Ä Ensure that the difference of potential between the negative generator connection and the local earth potential e g substructure PE of the inverter on each string in operati...

Page 11: ... or wear any electrically conductive parts WARNING Risk of falling due to unsecured access Ä Ä Never access the installation area alone or without taking adequate security precautions Ä Ä Please commission a trade specialist NOTE Module surface damage may occur Ä Ä Remove snow and ice carefully without force e g with a very soft broom Ä Ä Do not scratch off dirt Ä Ä Rinse dirt dust leaves etc off ...

Page 12: ...ee 17 21 06766 Bitterfeld Wolfen Germany TEL 49 0 34946699 23222 FAX 49 0 34946699 23000 EMAIL sales q cells com WEB www q cells com Subject to change without notice Q CELLS Installation manual solar modules Q PEAK DUO L G8 X_2019 05_Rev01_EN ...

Reviews: