background image

 

 

1

Installation And Operation Manual 

For 

DTPO610VC 

 

 

Forward this manual to all operators. Failure to operate this equipment as directed may cause injury.

  

 

  

 

 

INSTALLATION AND OPERATION MANUAL

 

 

                   

 

 

TWO POST LIFT 

 

MODEL NO. 

 

DTPO610VC 

 

Lifting Capacity

4.5T/10000lbs

 

Lifting Height

71in/1800mm 

 

Motor

2.2kw./3hp 

 

                                   

         

 

Keep this operation manual near the machine at all times. Make sure 
that ALL USERS read this manual.

     

 

                                                              

 

                                                                                        

 

SHIPPING DAMAGE CLAIMS

  

 

When  this  equipment  is  shipped,  title  passes  to  the 

purchaser upon receipt from the carrier. Claims for 
the material damaged in shipment must be made by 
the purchaser against the transportation company at 
the time shipment is received.

 

 

 

 

 

 

BE SAFE  

 

 

Your new lift was designed and built with safety in 

mind. However, your overall safety can be increased 
by  proper  training  and  thoughtful  operation  on  the 
part of the operator. DO NOT operate or repair this 
equipment  without  reading  this  manual  and  the 
important safety instructions shown inside.

 

 

Summary of Contents for DTPO610VC

Page 1: ...read this manual SHIPPING DAMAGE CLAIMS When this equipment is shipped title passes to the purchaser upon receipt from the carrier Claims for the material damaged in shipment must be made by the purchaser against the transportation company at the time shipment is received BE SAFE Your new lift was designed and built with safety in mind However your overall safety can be increased by proper trainin...

Page 2: ...WHICH IS LOCATED ON THE NAMEPLATE FOR OUR FOLLOW UP SERVICE Serial No Model No Manufacturing Date WARRANTY Your new lift is warranted for one years on equipment structure one year on all operating components to the original purchaser to be free of defects in material and workmanship The manufacturer shall repair or replace at their option for this period those parts returned to the factory freight...

Page 3: ...with all warranty claims PARTS INVENTORY PART S DESCRIPTION QTY WHERE USED CHECK Lift Pads 4 Lift Pads for Arms 3 Lift Pads Adapters 4 For Lift Pad Extensions 6 Lift Pads Adapters 4 For Lift Pad Extensions Fixing Pin 4 To link the Lifting Arm and Carriage Balancing Cables 2 Equalize Carriages Expansion Bolt 12 To concrete Columns Tee 1 Fixed on the Oil Cylinder Thread connected inside 1 Fixed on t...

Page 4: ...ach respectively 3 4 Pin 2 To fix Unlock Block Spring 2 To fix Unlock Block Oil cylinder 2 Fixed inside the column 3 8 Hex Nuts 4 To fix Release Cable φ2 5 Cable 1 For release Instruction Manual 1 Instruct operation Packing List Hydraulic Power Unit 1 Powerside Column 1 Power side Column with Carriage Cable and Cylinder Offside Column 1 Offside Column with Carriage Cable and Cylinder Coverplate Fl...

Page 5: ...he power unit used on this lift contains high voltage Disconnect power at the receptacle before performing any electrical repairs Secure plug so that it cannot be accidentally plugged in during service 14 WARNING RISK OF EXPLOSION This equipment has internal arcing or sparking parts which should not be exposed to flammable vapors This machine should not be located in a recessed area or below floor...

Page 6: ...uare Needle Nose Pliers IMPORTANT NOTICE Do not attempt to install this lift if you have never been trained on basic automotive lift installation procedures Never attempt to lift components without proper lifting tools such as forklift or cranes Stay clear of any moving parts that can fall and cause injury These instructions must be followed to ensure proper installation and operation of your lift...

Page 7: ...ditions NOTE All models MUST be installed on 2500 PSI concrete only conforming to the minimum requirements shown above New concrete must be adequately dried by at least 28 days Model No DTPO610VC A 145 3686mm B 17 432mm STEP 3 Site Layout 1 Determine which side will be the approach site 2 Now determine which side you prefer the power unit to be located on The POWERSIDE column has the power unit mo...

Page 8: ...move dust thoroughly out of each hole using compressed air and or wire brush Make certain that the column remains anchor bolts are tightened the columns will be plumb See Fig 3 aligned with the chalk line during this process 4 Assemble the washers and nuts on the anchors then tap into each hole with a hammer until the washer rests against the baseplate Be sure that if shimming is required that eno...

Page 9: ...9Installation And Operation Manual For DTPO610VC ...

Page 10: ...ne of the columns until the top beam is mounted STEP 6 Mounting the OVERHEAD BEAM Using a lifting device raise the OVERHEAD beam in position on top of the columns Bolt to the columns using the 3 8 x 40 Hex Bolts Nuts and Washers See Fig 5 NOTE Limit Switch is on side of the Powerside Column STEP 7 Mounting The HYDRAULIC POWER UNIT Attach the power unit to the POWERSIDE COLUMN using four 5 16 hex b...

Page 11: ...re proceeding 3 With the carriages in equal position from the floor route the equalizer cables as shown below See Fig 10 11 4 After the equalizer cables have been routed Adjust each cable so that they are of equal tension STEP 8 Routing The EQUALIZER CABLES Route the equalizer cables on each column See Fig 7 8 Adjust each cable so that they are of equal tension ...

Page 12: ...12Installation And Operation Manual For DTPO610VC 1 Raise and lock each carriage approximately 28 above the ground See Fig 9 2 Make sure that the safety locks on each column ...

Page 13: ...llation And Operation Manual For DTPO610VC STEP 9 Installing The Hydraulic Lines Install the hydraulic lines as shown below paying careful attention to keep the hoses clean and free of impurities See Fig 12 15 ...

Page 14: ...witch Install the overhead Limit switch as shown below AQUALIFIED ELECTRICIAN See Fig 16 STEP 11 Installing the Power Unit The standard power unit for your lift is 220 volt 50HZ and single phase All wirings must be performed by qualified electricians only SEE WIRING INSTRUCTIONS ATTACHED ON MOTOR FOR PROPER WIRING INSTRUCTIONS See Fig 17 IMPORTANT INSTALLATION NOTES DO NOT run power unit without o...

Page 15: ...OT press the button if the lift rises to the maximum height or it may result in power unit damage 3 Keep 5 6 seconds after the maximum height 4 Withdraw the release cable press the lowering handle to lower the lift 5 Repeat the following course WARNING During the whole lifting operation observe all the operational units to check the correctness of operation DO NOT lift vehicle when there is improp...

Page 16: ...16Installation And Operation Manual For DTPO610VC STEP 13 Installing Swing Arms 1 Install swing arms as described below Lubricate the carriage tube and all pivot point and pins prior to installation ...

Page 17: ...17Installation And Operation Manual For DTPO610VC ...

Page 18: ...t Always lift a vehicle according to the manufacturer s recommended lifting points Position vehicles between columns Adjust swing arms so that the vehicle is positioned with the center of gravity midway between pads Use truck adapters as needed Never exceed 9 of pad height Raise lift by pressing down button until supports contact the bottom of the vehicle Re check to make sure that the vehicle is ...

Page 19: ...o make sure that they are all properly secured Check the tensions of equalizer cables adjust if necessary Inspect all lift pads replace if necessary If lift is equipped with overhead cut off switch check for proper operation WARNING 1 If cement anchor bolts are loose or any component of the lift is found to be defective DO NOT USE LIFT 2 Never operate the lift with any person or equipment below 3 ...

Page 20: ...20Installation And Operation Manual For DTPO610VC LIFT WILL NOT RAISE ...

Page 21: ... check that motor is wired correctly Motor stops work Motor is out of work Replace with new one Incorrect voltage Fuse melted Replace with new limit switch MOTOR WILL NOT RUN Air in hydraulic oil Elevate to maximum height lower down after several seconds Repeat this procedure if necessary Cylinder leaking Tighten the loose pipe joint Replace oil seal around pump shaft Incorrect voltage Install vol...

Page 22: ...with new part Oil leaks from air hole Oil seal is out of work replace with new part Overabundant oil flowing out Decrease oil to proper content ABNORMAL NOISE Air in hydraulic oil Follow instruction above Lift overloaded Check the lifting weight Loose fixing bolt of the motor Screw up bolt Carriages lack of lubrication Fill up lubricant ...