Rev. 10/22/08

 

 

I

NSTALLATION

, O

PERATION 

& M

AINTENANCE 

M

ANUAL

 

Two Post 

Surface Mounted Lift 

 

M

ODEL 

Q10 

10,000 

LBS

. C

APACITY

 

2500 

LBS

PER 

A

RM

 

 

QUALITY LIFTS, LLC

 

200 Cabel St., P.O. Box 3972, Louisville, KY  40206 

FAX:  502-583-5488

 

TOLL FREE:  877-771-5438 

E-mail:  

sales@qualitylifts.com

 

www.qualitylifts.com

 

 

IMPORTANT:

  READ THIS MANUAL COMPLETELY BEFORE

 

INSTALLING or OPERATING LIFT 

Summary of Contents for Q10

Page 1: ...Lift MODEL Q10 10 000 LBS CAPACITY 2500 LBS PER ARM QUALITY LIFTS LLC 200 Cabel St P O Box 3972 Louisville KY 40206 FAX 502 583 5488 TOLL FREE 877 771 5438 E mail sales qualitylifts com www qualitylif...

Page 2: ...3314mm F Short Arm Reach 21 3 4 39 1 4 553mm 998mm G Long Arm Reach 38 1 4 55 3 8 971mm 1407mm H Screw Pad Height 4 1 4 7 3 4 109mm 199mm K Inside of Columns 110 1 4 2800mm Lifting Capacity 10 000 lbs...

Page 3: ...installation Failure by purchaser to provide the recommended mounting surface could result in unsatisfactory lift performance property damage or personal injury LOCATION This lift has been evaluated f...

Page 4: ...Arm Assembly 2 Synchronizer Cable Assembly 1 Hydraulic Hose Pack 1 Power Lock Cover 1 Idler Lock Cover INSTALLATION IMPORTANT Always wear safety glasses while installing lift TOOLS MINIMUM REQUIRED a...

Page 5: ...echeck column for plumb Re shim if necessary Torque to 150 foot pounds to set anchors OVERHEAD 11 Raise and install Overhead Assembly using M12 x 30 Hex Bolts 12 Install Overhead Limit Switch under th...

Page 6: ...Cord Lock Release Cable Hydraulic Hose Synchronizing Cables Fig 6 Hose Routing Power Side 23 Route the remaining Power column hose beginning at the elbow fitting at the base up the backside of the col...

Page 7: ...pressure relief will make a high pitch squeal sound for these 10 seconds Check hydraulic system for leaks 40 Energize power unit again for 10 seconds With a clean rag wipe down both cylinder rods The...

Page 8: ...1 5 4 6 Normally Open M Wiring Diagram A2 A1 T9 T5 T4 T6 M T8 T3 T7 T2 T1 1 2 3 4 5 6 L3 L2 L1 T3 T2 T1 FOR SINGLE PHASE FACTORY WIRED FOR 208 240V 6 4 2 5 3 1 RECONNECTIONS FOR 440 480V T3 T2 T1 T9...

Page 9: ...the lift inspectors are qualified and that they are adequately trained in the inspection of the lift The Owner Employer shall establish procedures to periodically maintain the lift in accordance with...

Page 10: ...he lock release lever 4 Lower the vehicle by depressing the lowering valve handle 5 Continue to lower the vehicle until the carriages stop against the base plate Retract the extension arms and park th...

Page 11: ...Model Q10 Installation Operation and Maintenance Page 11 Rev 10 22 08 Q10 IOM Q doc Parts Breakdown...

Page 12: ...Model Q10 Installation Operation and Maintenance Page 12 Rev 10 22 08 Q10 IOM Q doc...

Page 13: ...wl 61 JSJ5B 09 02 00CH 2 Rear Male Arm 17 X10 029 2 Washer 62 JSJ5B 09 01 00B 2 Rear Female Arm 18 X10 030 4 Pulley Axle 63 X10 073 6 Washer 10mm 19 X10 031 4 Pulley 64 X10 074 18 Spring Washer 10mm 2...