Please read these Operational and Installation Guidelines before installing the SmoothFlo® 

Series Pumps. If additional help is needed, please consult the Factory.

CAUTIONS

 

y

Water pipe connections and fixtures directly connected to a potable water supply shall 

be sized, installed and maintained in accordance with Federal, State, and local codes. 

 

y

Do not operate the pump above the pressure limitations specified on the data label. 

 

y

Never operate the pump in a harsh environment or hazardous atmosphere, since 

motor brush and switch may cause electrical arcing. 

 

y

Do not pump gasoline or other flammable liquids. Do not use with petroleum 

products.  

 

y

Do not assume fluid compatibility. If the fluid is improperly matched to the 

pumps’ elastomers, a leak may occur

 

y

As long as there is inlet water pressure, the pump will not stop forward flow of water 

even if the motor is turned off. Be sure the system has positive means of shutting off 

water supply.

 

y

Always consider electrical shock hazard when working with and handling electrical 

equipment. If uncertain, consult an Electrician. Electrical wiring should only be done 

by a qualified Electrician per Local and State Electrical Codes.

MOUNTING

 

y

The pump should be mounted in a dry place and away from any source of heat. If 

an enclosure is used, special instructions for cooling the motor may be necessary. 

Consult the Factory.

 

y

Do not subject the pump to extreme high or low (freezing) temperatures while in 

operation. (Operating ambient temperature range is 32ºF to 115ºF).

 

y

The pump may be mounted horizontally with the outlet port on the right when viewed 

from the pump end or with the pump above the mount; or vertically with the pump 

above or below the motor.

PLUMBING

 

y

The pump is equipped with either a pressure sensing demand switch, a bypass relief 

valve, or both which controls the maximum safe operating pressure.

 

y

We recommend use of flexible tubing with proper pressure rating.

 

y

Pump will prime only if all pressure is relieved from outlet port. 

 

y

It is recommended that debris-free liquid be pumped or an in-line sediment filter (50 

mesh) be installed at the inlet side to keep foreign debris out of the system.

 

y

The pump should always be mounted prior to any components which could introduce 

particles to the liquid; thus, preventing them from entering the pump chambers and 

possibly causing clogging.

 

y

Avoid any sharp bends which may crimp tubing and restrict flow. Use 90º elbow 

fittings if necessary. REMCO provides pumps with different kinds of fittings. Please 

consult Factory for your needs.

ELECTRICAL

 

y

The SmoothFlo® Series Pumps are designed for intermittent duty, but may run  

continuously if the motor temperature does not exceed the recommended limit. Some 

SmoothFlo® Series Pumps are equipped with thermally protected motors and in case 

motor temperature exceeds thermal cut-out rating, pump will shut down and will not 

restart until motor cools down to specified temperature. Please consult the appropri-

ate Data Sheet for continuous running parameters, noting the effect of rapid On/Off 

Cycling. (See section below)

 

y

If a power supply is used with the system and the supply is not furnished by  

REMCO, it will need to be reviewed for correct application and approval by REMCO.

Installation Procedure

The basic demand pump is controlled by a built-in pressure sensing demand switch. When 

a faucet or valve is opened down stream of the pump, line pressure drops, thus starting the 

pump automatically. Conversely, when the valve shuts, the line pressure increases turning 

the pump off automatically.  The pressure switch actuates in response to the pump outlet 

pressure at a predetermined and preset pressure. The pump label indicates the pre-set OFF 

pressures. Typically, the OFF pressure is accurately set at the FACTORY and the ON pressure 

is within an allowable range below that value. In response to the characteristics of the 

system in which the pump is installed, such as the flexibility and length of the tubing, and 

the faucet or valves and the duration that they are open, these pressure settings may vary. 

Therefore, change in pressure settings is expected with use and over time.  If the pump does 

not have an integral pressure sensing demand switch (i.e. pump is operated with an external 

control), pump will be equipped with a bypass relief valve (bypass is factory preset).

Read the OPERATIONAL AND INSTALLATION GUIDELINES on the other side carefully 

before starting to install the pump. Consult the Factory if there is any question.

Determine the optimum location for your pump before proceeding.

 

y

Turn off the fluid supply.

 

y

Cut the flexible tubing in sufficient length to avoid any stress on the tubing or hose 

where it connects to the pump or the fitting on any accessory or hose.

 

y

Insert tubing/hose into pump ports. If compression fittings with threaded nuts are 

used, insert tubing until it bottoms out in the port, hand tighten the compression nut 

until the connection is tight. Then use a wrench to tighten the nut 1/2 turn clockwise or 

follow the wrench tightening instructions provided by the fitting manufacturer. 

 

y

The SmoothFlo® Series pump is now ready for operation. Open the inlet valve if any to 

allow fluid to flow to the pump.

 

y

If the power source is a transformer, plug the appropriate REMCO  

supplied or approved transformer into the receptacle and connect the pump to the 

transformer. If the power source is not a transformer,  

connect the pump to the appropriate power source. Open the discharge or  

dispensing valve. Allow water to circulate, purging any entrapped air.

 

y

The pump will now start building pressure. Operating pressure will vary with flow rate, 

flow valve, feed-water pressure and line voltage. Check for fitting leaks.

 

y

If compression fittings with threaded nuts are used, observe any leaks after pump has 

run for approximately 15 minutes. Further tighten  

compression nuts approximately 1/8 to 1/4 of a turn on all fittings in the system. Wait 15 

minutes and repeat the leak check.

NOTE: Further adjustments should not be necessary although it may take several 

days of operation before all the air has been purged and the system is stabilized.

 

y

Rapid On/Off Cycling must be limited to no more than 6 times per minute, 

even if the pump is operating in the Continuous Duty zone. Cycling could 

cause the motor to heat beyond the recommended maximum temperature, 

and reduce the operational life of the pump and pressure-sensing switch.

Servicing

EVERY USE

Run clean water through the pump and  

system.

EVERY YEAR

Check system against operating standards. 

If continuous duty, replace lower housing 

assembly

EVERY OTHER YEAR

Check against operating standards. If 

continuous duty, replace motor

EVERY FIFTH YEAR

Replace pumphead

www.remcoindustries.com 