Smart Products
GHT Sliding Line
KXGHT
High flow
SIA 30/ XP20WD FAAC
Installation
1st -
Observe if the gate is sliding freely along its entire
route, observing
the support guide, rail, stops and pulleys, if not, correct it before installing
the automator.
2nd -
Provide a power and grounding point, passing a
conduit, starting
from the automator to the power panel with a 10A bipolar circuit breaker.
NOTE: It is mandatory to install a disconnection device (bipolar
circuit breaker with minimum contact opening equal to 3mm)
which must be incorporated into the attached wiring. 3rd -
Provide
the means by which you want to secure the automator.
• Concrete base • Metal base • French hand (air base) never upside
down.
Use the measurements in the manual to mark the location of the screws.
4th -
Place 2mm spacers (Ex. washers) on the base, screw the
automation
device on the spacers and put the actuator in manual mode.
5th -
Close the gate, support the rack on the gear and attach the bar to
the gate with welding or screw, every 30 cm.
6th -
After the racks are attached, remove the spacers placed
on the
base and attach the automator again, and check the spaces between the
rack and the gear.
NOTE:
" The spacers placed at the beginning of the attaching of the racks
serve to give the mandatory minimum height of
2mm between the rack
and the external gear of the automator.
“
NOTE:
" Failure to observe this distance can cause wear on the
internal and
external gears of the automator or the rack to break when the automator
starts."
7th -
Adjust the limit switches in
FA
open and
FF
closed mode,
placing a
magnet on each end of the rack angle, observing the polarity of each magnet
between the open and closed gate.
NOTE:
" The magnets must always be attached to the angle, even
during
the opening and closing adjustments to avoid damage to the control
panel"
8th -
Attaches the control unit to the support guide inside the automator
(instructions for attaching Page2).
9th - HALL
sensor limit switch
The hall sensor identifies the polarity of the magnets, north and south.
(instructions Page 6)
NOTE: For bench tests, it must simulate the movement of the magnet
installed in the gate, remembering that when activating the control, the
limit switch must be active.
When installing and adjusting the magnets, in the first two commands,
the control unit must recognize the FA and FF magnets.
10th -
It is MANDATORY to use the Active Infrared Sensor - SIA 30 FS or
XP20WD
wireless FAAC to activate the anti-trapping protection system, avoiding collision
with obstacles, accidents with people or material goods.
11th
- Gates and automations need periodic maintenance and lubrication
every 6 months for proper functioning.
1
support guide
Photocell x-ray
Pulleys
2
Circuit breaker
Photocell TX
Rail and Stop
3
4 5
6
Attachment points
2mm
Rev. E - COD. 14934
www.rossiportoes.com.br
Pag. 1