1st - 

Observe if the gate is sliding freely along its entire

 

route, observing 

the support guide, rail, stops and pulleys, if not, correct it before installing 

the automator.

 

 

2nd - 

Provide a power and grounding point, passing a

 

conduit, starting 

from the automator to the power panel with a 10A bipolar circuit breaker.

 

NOTE: It is mandatory to install a disconnection device (bipolar 

circuit breaker with minimum contact opening equal to 3mm) 

which must be incorporated into the attached wiring. 3rd - 

Provide 

the means by which you want to secure the automator.

 

 

• Concrete base • Metal base • French hand (air base) never upside 

down. 

Use the measurements in the manual to mark the location of the screws. 

4th  - 

Place 2mm spacers (Ex. washers) on the base, screw the 

automation

 

device on the spacers and put the actuator in manual mode. 

5th - 

Close the gate, support the rack on the gear and attach the bar to

 

the gate with welding or screw, every 30 cm. 

6th - 

After the racks are attached, remove the spacers placed

 

on the 

base and attach the automator again, and check the spaces between the 

rack and the gear. 

NOTE: 

" The spacers placed at the beginning of the attaching of the racks

 

serve to give the mandatory minimum height of

 

2mm between the rack 

and the external gear of the automator.

 “

 

  

NOTE: 

" Failure to observe this distance can cause wear on the

 

internal and 

external gears of the automator or the rack to break when the automator 

starts."

 

 

7th  - 

Adjust the limit switches in

  FA 

open and

  FF

  closed mode,

 

placing a 

magnet on each end of the rack angle, observing the polarity of each magnet 

between the open and closed gate.

 

NOTE: 

" The magnets must always be attached to the angle, even

 

during 

the opening and closing adjustments to avoid damage to the control 

panel"

 

 

8th - 

Attaches the control unit to the support guide inside the automator 

(instructions for attaching Page2).

 

 

9th -   HALL

 sensor limit switch

 

The hall sensor identifies the polarity of the magnets, north and south. 

(instructions Page 6)

 

NOTE: For bench tests, it must simulate the movement of the magnet 

installed in the gate, remembering that when activating the control, the 

limit switch must be active.

 

 

When installing and adjusting the magnets, in the first two commands, 

the control unit must recognize the FA and FF magnets.

 

10th - 

It is MANDATORY to use the Active Infrared Sensor - SIA 30 FS or

 

XP20WD 

wireless FAAC to activate the anti-trapping protection system, avoiding collision 

with obstacles, accidents with people or material goods.

 

 

11th 

-  Gates and automations need periodic maintenance and lubrication

 

every 6 months for proper functioning.

 

 

1

 

support guide

 

 

 

 

 

 

 

 

 

 

 

 

Photocell x-ray

 

Pulleys

 

 

 

                                                    2

 

 

                                                    Circuit breaker

 

 

 

 

Photocell TX

 

 
 

 
Rail and Stop

 

 

 

3

 

4                                           5

 

 

 

 

 

6

 

  

Attachment points

 

 

 

 

 

 

 

 

2mm

 

 

 

 

 