background image

Form 57032 Rev. A

01-05-2004

VIP 5100 OPEN ARCHITECTURE CYLINDRICAL LOCK

INSTALLATION MANUAL

5100 CYLINDRICAL

LOCKSET - STANDARD

The VIP 5100 series lock is a microprocessor controlled, electromechanical locking system.
It is an open architecture product designed to interface with 3rd party panels ecompassing
all the features of the lock, reader, door status* and egress (rex/request to exit) indication in
one fire-rated piece of hardware. The 5100 employs a heavy-duty mechanical design tested
and complying with ANSI/BHMA grade 1 standards for performance and reliability. It is pow-
ered by 12 or 24 volts DC with only four wires required - two for power and two for commu-
nications. The lock communicates with a PIB (panel interface board) which communicates
with the panel as if it were separate components of an access control system.

Operationally, the outside lever is normally locked and the inside lever always retracts the
bolt to allow egress. Electronic access control is achieved by entering an”Access Credential”
(magnetic stripe card or Prox fob or card). The panel controls the lock through the PIB.

*Cylindrical model requires separate door status switch (included) to be installed in the door
and frame and connected to the VIP lock.

Please refer to all instruction manuals involved in the installation before you begin. 

Functions:
VIP 5196-FSA: 

Cylindrical, Fail Safe (unlocked)

VIP 5196-FSE: 

Cylindrical, Fail Secure (locked)

Models:
MG:

Magnetic stripe card reader

PX:

HID Prox card reader

Standard Monitoring Switches:
DSM:

Provides door status via data link to panel interface

KSM:

Provides mechanical key use events via data link to panel interface

REX:

Provides indication of inside lever use for request to exit input via data link 

to panel interface

Options:
T3:

Track 3 card reader (data must be ABA track 2 format) - MG only

EXT:

exterior use option - MG only (PX model has this standard)

KD:

Keyed Different, includes Schlage Everest cylinder

KA:

Keyed Alike, includes Schlage Everest cylinder

LC:

Less Cylinder

SLB:

2-3/4” backset, 1/2”  latch bolt

OLB:

2-3/8” backset, 1/2” latch bolt

ELB:

2-3/4” backset, 3/4” latch bolt

BEFORE YOU BEGIN:

Standard units are shipped from the factory to fit 1-3/4” doors. Verify the
door thickness. If the door is not 1-3/4” thick, verify that the door thickness
option was ordered or consult factory.

PRE-INSTALLATION CHECK:
AN OPEN ARCHITECTURE SYSTEM REQUIRES AT LEAST THREE COMPO-
NENTS - A PANEL INTERFACE BOARD (PIB), AN ACCESS CONTROL PANEL
(BY OTHERS) TO WHICH THE PIB IS CONNECTED AND THE VIP LOCK. SEE
DOCUMENTATION FOR THE ACCESS CONTROL PANEL/SOFTWARE THIS
LOCK WILL BE USED WITH FOR ANY PRE-INSTALLATION TESTING REQUIRE-
MENTS AND REMEDIES. REFER TO THE WIRING INFORMATION INCLUDED
WITH THE PIB FOR MORE INFORMATION.

PIB

PX

MG

Door Thickness Kits:

Available in 1/8” increments from 1-3/8” to 2-1/2”

This device complies with part 15 of the FCC rules. Operation is subject to the following two conditions: (1) this device may
not cause harmful interference, and (2) this device must accept any interference received, including any interference that may
cause undesired operation. Changes or modifications not expressly approved by the party responsible for compliance could
void the user’s authority to operate the equipment.

Summary of Contents for VIP 5100 series

Page 1: ...hes DSM Provides door status via data link to panel interface KSM Provides mechanical key use events via data link to panel interface REX Provides indication of inside lever use for request to exit input via data link to panel interface Options T3 Track 3 card reader data must be ABA track 2 format MG only EXT exterior use option MG only PX model has this standard KD Keyed Different includes Schla...

Page 2: ... the retractor 3 Using appropriate drilling jig and drill bits drill 3 8 or 1 2 wire race from the latch hole through the door toward the hinge side It is not necessary to continue drilling the hole through the hinge side 4 Measure up 3 inches from the center of the 2 1 8 retractor hole and drill a 1 inch through hole on center as shown below 5 Using a 3 8 inch drill bit place the tip of the drill...

Page 3: ... centerlines for the lockset latch and strike C Place template on inside of door opposite the side that the keypad reader will be on Line up the correct reference lines on the template with the edge of the door The centerline on the door should line up with the vertical centerline of the tem plate D Drill holes as described by template DOOR EDGE LATCH FRAME STRIKE DOOR FACE LAY OUT ON INSIDE ...

Page 4: ...top facing out as shown below D Using nut tool provided tighten nut onto cylinder E Line up nearest notch on nut with tab on lock washer and bend tab using nut tool so nut is secure F Install exterior gasket if used G Install standoffs TEST KEY OPERATION NOW Turning key clockwise until it stops about 1 2 turn should allow the lever to turn retractor CYLINDER RECOMMENDED CAMS SCHLAGE EVEREST P N B5...

Page 5: ...signs have an adapter E Re install outside spindle making sure that the round end faces the handle and the spindle is positioned with its edges vertical and horizontal as shown in detail below Note that the cam inside the escutcheon assembly must be positioned such that the dot on it faces the 6 O Clock position see detail below F Rotate retractor and re install it G Change the hand of the handle ...

Page 6: ...LLATION MANUAL 4 INSTALL STRIKE BOX STRIKE AND DOOR SWITCH MAGNET 5 INSTALL LATCH AND DOOR STATUS SWITCH A Install latch into edge of door Be sure to install it with the beveled edge facing door jamb B Install switch as shown passing switch wires through to the inside of the door ...

Page 7: ...utside escutcheon onto door see detail for latch engagement Pass wiring harness through wire hole D Re install latch guard onto retractor 7 INSTALL INSIDE BASEPLATE ASSEMBLY SPACER FOR DOORS LESS THAN 1 3 4 SPACER FOR DOORS LESS THAN 1 3 4 SOCKET CAP SCREW WASHERS DATA POWER WIRES COME FROM HERE IF WIRING METHOD B WAS USED PASS THE WIRES THROUGH THIS HOLE IF A SPACER IS USED DRILL A HOLE IN THE SP...

Page 8: ...de lever to make sure that latch retracts fully IMPORTANT See PIB manual for additional connecting instructions SHIELD DATA B DATA A GROUND V 1 0A 12VDC 0 5A 24VDC OUTSIDE MAIN HARNESS CONNECTION OFF PARKED ON TERMINATION RESISTOR 1 LOCK ADDRESS SEE CHART 2 LOCK ADDRESS SEE CHART 3 ALWAYS SET TO OFF 4 ALWAYS SET TO OFF 5 OFF FAIL SECURE FSE ON FAIL SAFE FSA 6 OFF ALL MG LOCKS ON ALL PX LOCKS 7 NOT...

Page 9: ... escutcheon assembly onto inside baseplate using four screws IMPORTANT 1 MAKE SURE THAT INSIDE SPINDLE IS INSTALLED 2 PLUG REX SWITCH IN TO BOARD 3 DO NOT PINCH WIRES BETWEEN PARTS 10 SEE PIB MANUAL AND SYSTEM PANEL MANUAL FOR SET UP PROCEDURES INSIDE SPINDLE PLUG REX SWITCH INTO PC BOARD DO NOT PINCH WIRES FOR REX SWITCH BETWEEN PARTS ...

Reviews: