Installation Instructions

Assembly of Boiler Sections,

Part No. 7134 271

for Vertomat VSB-17 to -89

and Vitocrossal 300, CT3-17 to -89 boilers

5285 410 v1.1 11/2007

Safety and Installation Requirements

Please ensure that these instructions are read and understood before commencing installation. Failure to comply

with the

instructions listed below can cause

product/property damage

,

severe personal injury

, and/or

loss of life

.

Working on the equipment

The installation, adjustment, service,

and maintenance of this product must

be done by a

licensed professional

heating contractor

who is qualified and

experienced in the installation, service,

and maintenance of hot water boilers.

There are no user serviceable parts on

the boiler, burner, or control.

Ensure

main power

supply to

equipment, the heating system, and all

external controls has been

deactivated

.

Close

main

gas supply valve

. Take

precautions in all instances to avoid

accidental activation of power during

service work.

Ensure that the installation
literature of other components
is referenced.

Assembly Instructions

Never put any tools, bolts or any other
parts inside the combustion chamber.

1.

Clean combustion chamber surfaces
with stainless steel wire brush
5”/127 mm from the edges.

Do not use solvents. Use only clean
towels and/or rags.

2.

Apply supplied tape

on the edge

of the front cone section as
illustrated, and finish with 3”/76 mm
loop tabs.

3.

Apply supplied tape

3

/

8

“/10 mm

from edge of main boiler section as
illustrated, and finish with 3”/76 mm
loop tabs.

4.

Apply generous amount of supplied
Dirko silicone evenly between the
combustion chamber edge and the
steel ring welded to the front
section

.

Do not discard empty tubes! Empty
tubes are used for removal of excess
silicone. See next step.

Please

file

in

Service

B

inder

Fig. 1
Assembly of combustion chamber

IMPORTANT

IMPORTANT

Reviews: