3.3
Creating Program Patterns
The following operating procedure describes an example of creating the program dis-
cussed in “3.1 Overview of Program Patterns.”
NOTE
Before creating the program, reverify the Maximum Value of PV Input Range (RH), Mini-
mum Value of PV Input Range (RL), Program Time Unit (TMU), and Segment Setting
Method (SEG.T) parameters.
If the setting of the setup parameter “SEG.T” is changed, the program patterns created and
stored so far will be all cleared (initialized) !! Be careful.
The programming example given in this section includes the following steps.
•
Steps 4 to 9 configure the PV Event 1 parameter (i.e., a procedure for outputting an
alarm if the temperature goes beyond the range “program setpoint
⫾
5
⬚
C.”)
•
Step 10 configures the PV Event 2 parameter (not configured here).
•
Steps 11 to 13 configure the On time of Time Event (1.EON) parameter.
•
Steps 14 to 16 configure the Off Time of Time Event (1.EOF) parameter .
•
Steps 17 to 19 configure the Starting Target Setpoint (1.SSP) parameter.
•
Step 20 configures the Start Code (1.STC) parameter (not configured here).
•
Steps 21 to 23 configure the Segment-1 Target Setpoint (1.SP1) parameter.
•
Steps 24 to 26 configure the Segment-1 Segment Time (1.TM1) parameter.
•
Step 27 configures the Segment-2 Target Setpoint (1.SP2) parameter.
•
Steps 28 to 30 configure the Segment-2 Segment Time (1.TM2) parameter.
•
Steps 31 to 33 configure the Segment-3 Target Setpoint (1.SP3) parameter.
•
Steps 34 to 36 configure the Segment-3 Segment Time (1.TM3) parameter.
1st Edition : May 31,2000-00
Summary of Contents for UP350
Page 2: ...Blank Page ...
Page 52: ...Blank Page ...
Page 62: ...Blank Page ...
Page 72: ...Blank Page ...
Page 94: ...Blank Page ...
Page 96: ...Blank Page ...